The developers with the most projects cleared here — open any for its own dossier.
02
Track record over time
When it cleared projects, and when the filed pipeline is due to complete.
Approvals per year
Completion pipeline
By each project’s filed (or revised) possession year.
03
On the record
What the record shows about the projects it cleared — facts about those filings, never a verdict on the authority.
1
Marked complete
7
Still ongoing
1 project with a lapsed, revoked, surrendered or in-abeyance registration.
Completion status, complaints and litigation are carried only where the state authority publishes them, and many do not. An absent signal is silence, not proof — verify with the authority.
04
The projects
8 on the record
Plotted
Irrigation Department Officers and Employees Housing Scheme, Hingna
Vidarbha Patbandhare Karmachari Sahakari Pat Sanstha Maryadit · Hingna
3 yr 2 mo
Oct 2025registered
Dec 2028target completion
Plots81 plotsLand area13,145 sq mRecreational open space2,082 sq m