Municipal / local body · dossier
Lonavala Municipal Council Municipal body · Maharashtra
gethorizon.in/authorities/lonavala-municipal-council Lonavala Municipal Council has approved 9 projects on the public RERA record, filed by 7 builders, registered 2017–2023.
What it clears
Residential 100%
01
Caseload, summed Everything declared at registration across the projects this authority cleared, added up.
9 Projects
3 Active now
7 Builders
2017–2023 On the record
104 flats declared
23,682 sq m built-up declared Clears mostly apartment projects.
Every figure is drawn from the official RERA government registers — as each project declared it.
Where they authorize Mawal 8 projects Kurla 1 projects Who builds under it The developers with the most projects cleared here — open any for its own dossier.
02
Track record over time When it cleared projects, and when the filed pipeline is due to complete.
Approvals per year 4 ’17 1 ’18 0 ’19 1 ’20 2 ’21 0 ’22 1 ’23 Completion pipeline By each project’s filed (or revised) possession year.
03
On the record What the record shows about the projects it cleared — facts about those filings, never a verdict on the authority.
3 complaints on the record, across 2 projects. 3 projects with a lapsed, revoked, surrendered or in-abeyance registration. Completion status, complaints and litigation are carried only where the state authority publishes them, and many do not. An absent signal is silence, not proof — verify with the authority.
04
The projects 9 on the record Residential / Group Housing
STELLAR 8 Iraah Lifespaces LLP · Lonavala (M Cl) · Mawal
2 yr 5 mo
Feb 2023 registered
Jul 2025 target completion
Units 8 unitsFloors 2Buildings 12
Residential / Group Housing
U. S. Residency New Modern Buildwell Private Limited · Lonavala (M Cl) · Mawal
4 yr
Jun 2021 registered
Jun 2025 target completion
Units 10 unitsMix 10 × Bungalow / VillaCarpet area 91–122 sq m
Residential / Group Housing
Manorath Samarth Realty · Lonavala (M Cl) · Mawal
3 yr 1 mo
Mar 2021 registered
Apr 2024 target completion
Units 42 unitsFloors 4Buildings 2
Residential / Group Housing
Olympiodoros Phase - II Neel Buildcon · Lonavala (M Cl) · Mawal
6 yr 11 mo
Jul 2020 registered
Jun 2027 target completion
Units 13 unitsFloors 5Buildings 26
Residential / Group Housing
Olympiadorous Phase I Neel Buildcon · Lonavala (M Cl) · Mawal
5 yr 1 mo
Nov 2018 registered
Dec 2023 target completion
Units 7 unitsFloors 5Buildings 8
Residential / Group Housing
CANVAS PDS REALTY PRIVATE LIMITED · Lonavala (M Cl) · Mawal
2 yr 4 mo
Aug 2017 registered
Dec 2019 target completion
Units 18 unitsFloors 4Buildings 18
Residential / Group Housing
Infina Gardens Infina Ashapura Homes LLP · Kurla
3 yr 3 mo
Aug 2017 registered
Nov 2020 target completion
Units 6 unitsFloors 4Buildings 5
Residential / Group Housing
Sayama Phase 2 Puranik Builders Limited · Lonavala (M Cl) · Mawal
11 yr 4 mo
Aug 2017 registered
Dec 2028 target completion
Floors 16Buildings 4Parking 10 spaces
Residential / Group Housing
Sayama Phase 4 Puranik Builders Limited · Lonavala (M Cl) · Mawal
19 yr 4 mo
Aug 2017 registered
Dec 2036 target completion
Floors 16Buildings 18Parking 67 spaces