Developer · builder dossier
Commissioner
Karnataka
gethorizon.in/builders/commissionerCommissioner has 7 projects on the public RERA record across 1 state, filed under 5 approving authorities, first registered 2021 through 2025.
What they build
Residential 100%
01
Portfolio, summed
Everything the builder declared at registration, added up across the projects on the record.
- 7
- Projects
- 6
- Cities
- 2021–present
- On the record
- 5
- Authorities
- 4,134
- flats declared
- 1,51,560 sq m
- built-up declared
- ₹1031.60 Cr
- declared build cost
Typical filed home size 270–2,570 sq ft (median 460) · built-up as filed, from 4 projects that carry unit areas.
Every figure is drawn from the official RERA government registers — as each project declared it, not an independent measurement.
Where they build
Top cities
- Hubballi2 projects
- Bhadravathi1 projects
- Karkala1 projects
- Ballari1 projects
- Shivamogga1 projects
- Kalaburagi1 projects
Who approves them 5 authorities
- Hubballi Dharwad Municipal Corporation2 projects
- Shivamogga Urban Development Authority2 projects
- KSDB - Karnataka State Slum Development Board1 projects
- Bellary Urban Development Authority1 projects
- Kalburgi Urban Development Authority1 projects
The planning authorities that signed these projects off, read from each filing’s approval record — not every state files the approving body, so this covers the projects where it’s on record.
02
Track record over time
When their projects were registered, and when the filed pipeline is due to complete.
Completion pipeline
By each project’s filed (or revised) possession year.
Timelineevery project, start → promised completion
20192020202120222023202420252026202720282029today
03
On the record legally
What the public register carries about delivery and disputes — facts to raise in a meeting, never a verdict.
- 0
- Marked complete
- 7
- Still ongoing
- 4
- Possession date passed
No complaints, lapsed projects or declared litigation appear on the record for the projects read here — where the state authority publishes them.
Projects carrying a flag on the record
Complaints, litigation and escrow are shown only where the state authority publishes them, and many do not. An absent signal is silence, not proof of a clean record — verify with the authority and your own lawyer.
04
The projects
7 on the recordResidential/Group Housing
Construction of 250 DU's in Karkala town.
Commissioner · Karkala
3 yr
Dec 2022started
Dec 2025target completion
Land area24,282 sq mCovered area16,188 sq mOpen area8,094 sq m
Apartment
Construction of 2048 houses at Bhadravathi
Commissioner · Bhadravathi
5 yr 2 mo
Feb 2024started
Apr 2029target completion
Units2,048 unitsUnit mix2048 × HousesTowers1
Apartment
construction of 784 houses at Hubli
Commissioner · Hubballi
5 yr
Nov 2023started
Nov 2028target completion
Units784 unitsUnit mix784 × housesTowers1
Apartment
construction of 1248 houses at Hubli
Commissioner · Hubballi
5 yr 1 mo
Mar 2023started
Apr 2028target completion
Units1,248 unitsUnit mix1248 × HousesTowers1
Residential/Group Housing
PMAY AHP G+2 5616 DUs Project
Commissioner · Ballari
4 yr 6 mo
Sep 2019started
Mar 2024target completion
Land area2,36,741 sq mCovered area1,68,584 sq mOpen area68,157 sq m
Apartment
PKGB 214
Commissioner · Kalaburagi
2 yr 2 mo
Mar 2020started
May 2022target completion
Units54 unitsUnit mix54 × FlatTowers2
Residential/Group Housing
Construction of 3000 Du's (G.F + 2 Floors) and In
COMMISSIONER · Shivamogga
2 yr
Jun 2021started
Jun 2023target completion
Land area1,82,510 sq mCovered area1,82,510 sq mOpen area20,274 sq m