Commonly-controlled group · dossier

Atul

Maharashtra

gethorizon.in/builders/groups/maha-atul

2 legally separate firms the RERA record shows are controlled by the same people — 4 projects across Maharashtra, on the record since 2017.

Each firm carries its own liability. A shared track record is context for who is behind a project — not a guarantee for any one project.

What they build
Residential 100%

The firms in this group

2 on the record

Each is a legally separate company with its own liability — the record shows the same people control them. Any flag stays attributed to the firm that carries it.

Portfolio, summed

Everything the group's firms declared at registration, added up across all their projects on the record.

4
Projects
2
Filed firms
3
Cities
2017–2024
On the record
2
Authorities

What they build

4projects
  • Residential4 100%

Where they build

  • Maharashtra4 projects

Top cities

  • Andheri2 projects
  • Borivali1 projects
  • Kurla1 projects

Who approves them 2 authorities

  • Municipal Corporation of Greater Mumbai1 projects
  • Slum Rehabilitation Authority1 projects

Track record over time

When the group's projects were registered, and when the filed pipeline is due to complete.

New projects each year

117018019220124

Completion pipeline

130

By each project’s filed (or revised) possession year.

Timelineevery project, start → promised completion

The projects

4 on the record
Residential / Group Housing

BLUE FORTUNA PHASE II

ATUL PROJECTS INDIA PRIVATE LIMITED · Andheri

Sep 2020registered
Sep 2023target completion
Units13 unitsFloors5Buildings2
Residential / Group Housing

SAMARTH BLUE MOUNTAINS

ATUL PROJECTS INDIA PRIVATE LIMITED · Borivali

Jan 2020registered
Mar 2025target completion
Units78 unitsMix39 × 3 BHK · 38 × 2 BHK · 1 × 5 BHKCarpet area65–217 sq m
Residential / Group Housing

BLUE FORTUNA

ATUL PROJECTS INDIA PRIVATE LIMITED · Andheri

Aug 2017registered
Sep 2020target completion
Units175 unitsCarpet area42–346 sq mMix61 × 1 BHK · 52 × 2 BHK
Residential / Group Housing

Atul Life Phase I

ATUL PROJECTS INDIA PVT LTD · Nahur · Kurla

Apr 2024registered
Dec 2030target completion
Units632 unitsFloors50Buildings4

How we grouped these: the RERA filings for these firms name the same controlling partners — they share 3 in common. We show only the firms and counts, never the individuals. The grouping is context for who is behind a project, not a verdict; each firm remains a separate legal entity, and nothing on this page is a rating, a ranking or a prediction.

Full dossier: gethorizon.in/builders/groups/maha-atul