SRIJAN RESIDENCY LLP has 10 projects on the public RERA record across 1 state, filed under 3 approving authorities, first registered 2023 through 2025.
What they build
Residential 90%Mixed 10%
01
Portfolio, summed
Everything the builder declared at registration, added up across the projects on the record.
10
Projects
6
Cities
2023–present
On the record
3
Authorities
2,547
flats declared
2,72,802 sq m
built-up declared
Typical filed home size 870–1,970 sq ft (median 1,220) · built-up as filed, from 10 projects that carry unit areas.
Every figure is drawn from the official RERA government registers — as each project declared it, not an independent measurement.
What they build
Residential9 90%
Mixed1 10%
Where they build
West Bengal10 projects
Top cities
Maheshtala3 projects
Rajarhat3 projects
PS. Taratala1 projects
Madhyamgram1 projects
Rajpur Sonarpur1 projects
Sonarpur1 projects
Who approves them 3 authorities
Gram Panchayat2 projects
Madhyamgram Municipality1 projects
Rajpur-Sonarpur Municipality1 projects
The planning authorities that signed these projects off, read from each filing’s approval record — not every state files the approving body, so this covers the projects where it’s on record.
02
Track record over time
When their projects were registered, and when the filed pipeline is due to complete.
New projects each year
Completion pipeline
By each project’s filed (or revised) possession year.
What the public register carries about delivery and disputes — facts to raise in a meeting, never a verdict.
0
Marked complete
10
Still ongoing
0
Possession date passed
No complaints, lapsed projects or declared litigation appear on the record for the projects read here — where the state authority publishes them.
Complaints, litigation and escrow are shown only where the state authority publishes them, and many do not. An absent signal is silence, not proof of a clean record — verify with the authority and your own lawyer.
04
The projects
10 on the record
Residential
Optima Phase 2
SRIJAN RESIDENCY LLP · Rajarhat
4 yr 11 mo
Jan 2025registered
Dec 2029target completion
Apartments175Land area6,292 sq mBuilt-up area19,358 sq m