Complete project overview

HRERA Gurugram · Registration filing
Units
622 units
Land area
49,954 sq m
Parking
1,817 spaces
DTCP licence no.
69 of 2012the Haryana Town & Country Planning colony licence — verifiable on the DGTCP Haryana portal
Statutory approvals
6 declared obtained · Fire, Service, Height, Forest, Aravaliclearances the promoter declared obtained at registration — not independently verified here
Revised completion
30 Jun 2021revised completion date the promoter filed with HRERA — later than the original

Timeline

Project startedSep 2012
RERA registeredNov 2018
Proposed completionDec 2019
TodayJul 2026
Construction progress

65% overall, as filed

The % of external / site infrastructure (roads, water, sewerage, electrical) the promoter declared complete when this project was registered with HRERA — a snapshot at registration, and infrastructure, not building / tower construction. Not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

48 of 622 available
TypeArea sq mAvailable
TOWER-A - 3B+3T+SQ(1)1052 of 50
TOWER-A - 3B+3T (L1)940 of 21
TOWER-A - 3B+3T (L2)920 of 21
TOWER-B -2B+2T640 of 60
TOWER-B -3B+3T841 of 15
TOWER-B -3B+3T(1)850 of 15
TOWER-C - 3B+3T+SQ.1051 of 15
TOWER-C - 3B+3T (L2C)940 of 15
TOWER-C - 3B+3T (L1C)921 of 15
TOWER-C - 3B+3T (C)840 of 14
TOWER-D - 3B+3T+SQ.1054 of 39
TOWER-D - 3B+3T(L1C)941 of 20
TOWER-D - 3B+3T(L2C)921 of 20
TOWER-E -3B+3T+SQ.1052 of 39
TOWER-E -3B+3T(L2C)920 of 20
TOWER-F -3B+3T+SQ.1051 of 15
TOWER-F -3B+3T (L1C)920 of 15
TOWER-F -3B+3T (L2C)940 of 15
TOWER-F -3B+3T (C)840 of 14
TOWER-G - 2B+2T640 of 60
TOWER-G - 3B+3T840 of 15
TOWER-G - 3B+3T(1)850 of 15
TOWER-H - 4B+4T+SQ.1659 of 45
TOWER-H - PENTHOUSE-1: PH3030 of 1
TOWER-H - PENTHOUSE-2: PH3031 of 1
TOWER-I - 4B+4T+SQ.16522 of 45
TOWER-I - PENTHOUSE-1: PH3031 of 1
TOWER-I - PENTHOUSE-2: PH3031 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

HRERA Gurugram · Promoter registration

chddevelopers.com

CompanyPromoter type
Gurugram, HaryanaBased in
569 units · completed 28 Jul 2021Prior registered project
Declared under litigationPrior project litigation
1Projects
1City
2018–2019Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

HRERA Gurugram · Registration filing
Address
SECTOR- 106, GURUGRAM
Tehsil
GURGAON
District
GURUGRAM
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.2km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 759 m · Dwarka ExpresswayPrimary road 4.6 kmRailway line 1.6 kmRailway station 1.7km away (Gurgaon)Limited bus connectivity nearby
Water & environment
Water body 479 mRiver 3.1 km · Sahibi River
distances only — not a flood assessment
Land, title & encumbrance
Land licencePromoter is the licence holder for the land
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

HRERA Gurugram · Approved building plan

Directorate of Town & Country Planning, Haryana (DTCP)

Town & Country Planning (DTCP)
Building Permit

The promised possession date (31 Dec 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — HRERA Gurugram does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — HRERA Gurugram does not publish a complaints register. This read cannot speak to them either way.