Complete project overview
RAJ-RERA · Registration filing- Units
- 210 units
- Mix
- 120 × 2bhk · 40 × 1bhk · 7 × SHOP (17,18,20,24,25,28 &29) · 7 × SHOP (2,3,6,7,11,13 & 14) · 6 × SHOP (38,39,41,46,48 & 49) · 4 × SHOP (42,43,44&45)
- Carpet area
- 8–40 sq mper-type range, as filed
- Land area
- 26,009 sq m
- Completion deadline extended
- 2 extensions on record — latest to 5 Mar 2023declared reason: force majeure
- Description
- UIT UDAIPUR HAS APPROVED PROJECT UNDER CMJAY 2015 ON LAND 17200 SQMT OUT OF TOTAL LAND 26009.42 SQMT AND THE PROJECT IS BEING SUBMITTED FOR THE SAME IN RERA REGISTRATION. AS OF NOW THE PROJECT IS APPROVED IN PHASE MANNER, IN 1ST PHASE AS PER UIT UDAIPUR LETTER DATED 06-09-2017 POINT NO. 5 & 6 PERMISSION FOR STILT + GROUND FLOOR TO FIFTH FLOOR WITH COMPLETION TIME PERIOD 30 MONTHS. 2. APPROVED SITE PLAN ENCLOSED HEREWITH MAY KINDLY BE TREATED AS TYPICAL FLOOR PLAN (WHICH IS SAME ON ALL FLOORS APPROVED BY UIT) ALSO AS THE SAME HAS BEEN APPROVED BY UIT UDAIPUR. REVISED MAPS WITH SUBSEQUENT CHANGES ARE UPLOADED ON 6/8/2019.
Timeline
Find your flat
Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
Builder’s track record
RAJ-RERA · Promoter registrationaasan affordable housing LLP
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location & price analysis
RAJ-RERA · Registration filing- Address
- 2815m,3613/2815,2816,2817,3624/2818,2818, near riico industrial area kaladwas, kaladwas, Girwa, Udaipur, 313003
- Village
- kaladwas
- Taluka
- Girwa
- District
- Udaipur
- Pincode
- 313003
₹68.25 Cr declared to build 210 flats. What that works out to:
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Planning authority
RAJ-RERA · Approved building planThe promised possession date (5 Mar 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.