Complete project overview

RERA Madhya Pradesh · Registration filing
Units
24 flats
Revised completion
24 May 2027extended after an approved RERA extension
Extensions
1 approved · Normalcompletion-date extension(s) granted by RERA
Quarterly reports
8 on file · latest Apr 2024 - Jun 2024quarterly progress certificates filed with RERA

Timeline

Project startedJul 2024
RERA registeredJul 2024
Proposed completionMay 2026
TodayJul 2026
02

Builder’s track record

RERA Madhya Pradesh · Promoter registration

ASNANI BUILDERS AND DEVELOPERS LIMITED

CompanyPromoter type
4Projects
2Cities
2019–2026Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
753 homeson the public record across 4 projects
₹279.41 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Madhya Pradesh · Registration filing
District
Bhopal
Tehsil
Kolar
Planning area
Bhopal
Address
Khasra No. 129/4, 129/9, 130/1, 131/1/1, 131/2, 131/3/1, 131/4/2, 132/1/5, 133, 134, 135, 136, 137/1, 137/2, 138/1, 138/2, 139/1 and 140 at village Katara, Tehsil – Kolar, Jila Bhopal, M.P.
Price analysisdeclared build cost — not a sale price

₹101.41 Cr declared to build 24 flats. What that works out to:

₹4.23 Crdeclared cost per flatall-in — land + construction
33%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Madhya Pradesh · Approved building plan

Bhopal

Town & Country Planning (DTCP)
Building Permit

The promised possession date (24 May 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Bhopal

Town & Country Planning area · Bhopal district

Has approved 726 RERA projectsabout 1 in 7 in Madhya Pradesh.

a mixed market63% apartments · 37% plotted layouts.

Builders
444
On record
45,421 flats · 32,913.65 plots
Reach
2 tehsils
Since
2017

More apartment-heavy than Madhya Pradesh overall — 63% apartments here vs 28% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — RERA Madhya Pradesh does not publish a complaints register. This read cannot speak to them either way.