Plots
116 plots
Land area
29,800 sq m
Description
1). As per Township Policy 2010, 15 Plots (Plot No. 40, 74 TO 80, 82, 83, 84, L-11, E-12, E-17, E-18) having Total area of 1748.36 Sq. Mtrs equal to 12.5% of saleable area have been kept as mortgage under Nagar Palika Keshoraipatan. These plots would be allotted after the internal development work of project is completed and development charges are deposited with Nagar Palika Keshoraipatan. 2). Since it is a plotted development project therefore no parking details are required. 3. The Total Open Area 14844.80 Square meters and the area related with Safety Road/Park 2465.68 Sq Mtr, Road 11859.77 Sq Mtr and apart from that area of FACILITY is 1494.90 Sq Mtr.

Timeline

Construction startDec 2025
RERA registeredMar 2026
Proposed completionApr 2027
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

116 plots across 53 batches
TypeArea sq mCount
Plot1511
Plot1221
Plot1281
Plot1351
Plot1411
Plot1471
Plot1541
Plot1601
Plot1392
Plot1481
Plot421
Plot311
Plot371
Plot1181
Plot1396
Plot1341
Plot1161
Plot1531
Plot1165
Plot501
Plot1021
Plot1011
Plot1412
Plot2481
Plot3981
Plot2281
Plot2191
Plot2371
Plot1393
Plot1501
Plot1681
Plot1771
Plot1398
Plot2881
Plot1168
Plot2281
Plot1761
Plot1166
Plot937
Plot831
Plot1401
Plot937
Plot1161
Plot1631
Plot411
Plot411
Plot429
Plot423
Plot311
Plot5961
Plot5610
Plot561
Plot451

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

MAHAVEER RATHORE

IndividualPromoter type
Bundi, RajasthanBased in
1Projects
1City
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
452, 453, KESHORAIPATAN, KESHORAIPATAN, Keshoraipatan, Bundi, 323601
Village
KESHORAIPATAN
Taluka
Keshoraipatan
District
Bundi
Pincode
323601
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.7km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 3.0 kmRailway line 3.1 kmRailway station 3.2km away (Keshorai Patan)Limited bus connectivity nearby
Water & environment
Canal 1.2 kmRiver 1.8 km · Chambal River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹3.50 Cr declared to build 116 plots. What that works out to:

₹3.02 Lakhdeclared cost per plotall-in — land + construction
₹109/sq ftof plotted area₹1,174/sq m
57%of the cost is land₹62/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Senior Town Planner

Town & Country Planning
Layout Permitapproved 30 Oct 2025 · 9 mo ago
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Town Planning office

The state Senior Town Planner's office. It has approved 115 RERA projects across 18 districts about 1 in 19 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.