Complete project overview

RERA Telangana · Registration filing
Units
50 units
Unit mix
30 × 2BHK, 20 × 3BHK
Saleable area
116–148 sq mper unit, as filed
Floors
5
Land area
2,308 sq m
Built-up area
5,671 sq m

Timeline

RERA approvedSep 2019
Proposed completionMar 2023
TodayJul 2026
Construction progress

90% overall, as filed

Podiums0%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

9 of 50 available
BuildingFloorTypeArea sq mAvailable
AASTHAS GREEN SPACE13BHKmortgaged1421 of 1
AASTHAS GREEN SPACE12BHKmortgaged1163 of 3
AASTHAS GREEN SPACE13BHK1410 of 1
AASTHAS GREEN SPACE12BHK1180 of 3
AASTHAS GREEN SPACE13BHKmortgaged1482 of 2
AASTHAS GREEN SPACE23BHK1410 of 1
AASTHAS GREEN SPACE22BHK1160 of 3
AASTHAS GREEN SPACE23BHK1420 of 1
AASTHAS GREEN SPACE23BHK1480 of 2
AASTHAS GREEN SPACE22BHK1180 of 3
AASTHAS GREEN SPACE33BHK1410 of 1
AASTHAS GREEN SPACE32BHK1160 of 3
AASTHAS GREEN SPACE33BHK1420 of 1
AASTHAS GREEN SPACE33BHK1480 of 2
AASTHAS GREEN SPACE32BHK1181 of 3
AASTHAS GREEN SPACE43BHK1410 of 1
AASTHAS GREEN SPACE42BHK1160 of 3
AASTHAS GREEN SPACE43BHK1420 of 1
AASTHAS GREEN SPACE43BHK1480 of 2
AASTHAS GREEN SPACE42BHK1180 of 3
AASTHAS GREEN SPACE52BHK1182 of 3
AASTHAS GREEN SPACE53BHK1410 of 1
AASTHAS GREEN SPACE52BHK1160 of 3
AASTHAS GREEN SPACE53BHK1480 of 2
AASTHAS GREEN SPACE53BHK1420 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

AASTHA GREEN HOMES

PartnershipPromoter type
Hyderabad, TelanganaBased in
2Projects
1City
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
297 homeson the public record across 2 projects
54,984 sq mbuilt-up filed
9,996 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
OSMAN NAGAR VILLAGE
Village
OSMANNAGAR
Mandal
RC PURAM
District
Sangareddy
Pincode
502032
North boundary
ROAD
East boundary
GOLLA LAXMI AGRICULTURE LAND
South boundary
KAVALI VEERAIAH AGRICULTURE LAND
West boundary
DAKUR RAMULU AGRICULTURE LAND
What’s nearby
SchoolsNearest school 1.1km away
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 3.2 km · Shankarpalli RoadRailway line 3.5 kmRailway station 3.9km away (Telapur)Limited bus connectivity nearby
Water & environment
Water body 2.6 km
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land, Wet Land double crop. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Water supply100%
Sewerage (Chamber,…100%
Green Strip/TOT LO…100%
Rainwater100%
Electricity100%
Aggregate area of …100%
Roads0%
Rainwater0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Renewable energy0%
Fire safety0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 4/EE1 & 4/EE1/2

The promised possession date (31 Mar 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.