HORIZONMarkets
01

Complete project overview

RERA Karnataka · Registration filing
Status
Completed
Towers
1
Land area
1,163 sq m
FAR sanctioned
2.48
Covered area
390 sq m
Open area
774 sq m

Timeline

Project startedDec 2016
RERA registeredOct 2017
Proposed completionDec 2019
TodayJul 2026
02

Builder’s track record

RERA Karnataka · Promoter registration

Ajmera Housing corporation, Bangalore

Bengaluru UrbanBased in
6Projects
3Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
545 homeson the public record across 6 projects
85,941 sq mbuilt-up filed
52,803 sq mland declared
₹591.21 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Bengaluru South
District
Bengaluru Urban
Pincode
560076
Address
Survey no 100/P, Doddathogur Village, Begur Hobli
What’s nearby
Schools3 schools within 1km · 5 educational institutions within 1km · College or university 1.9km away
HealthcareHospital 381m away · 3 clinics within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · 15+ restaurants and cafes within 1km
ShoppingSupermarket 1.1km away · Convenience store within 500m · Bank 545m away
Getting around
Expressway 90 mPrimary road 5.0 km · Silkboard Double Decker FlyoverMetro station 598m away (Singasandra)2 bus stops within 500m
Water & environment
Water body 477 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹3.86 Cr declared. What that works out to:

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

BDA - Bangalore Development Authority

Urban Development Authority
Building Permit

The promised possession date (31 Dec 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

BDA

Urban Development Authority · Bangalore Development Authority

Has approved 830 RERA projectsabout 1 in 11 in Karnataka.

an apartments market73% apartments · 27% plotted layouts. Apartments like yours are this body's core business.

Builders
626
On record
82,843 flats · 16,515 plots
Reach
13 taluks
Since
2017

More apartment-heavy than Karnataka overall — 73% apartments here vs 62% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.