Complete project overview

RERA Telangana · Registration filing
Units
22 units
Unit mix
22 × 3BHK
Saleable area
158–186 sq mper unit, as filed
Floors
6
Land area
1,960 sq m
Built-up area
7,955 sq m

Timeline

RERA approvedMar 2022
Proposed completionMar 2027
TodayJul 2026
Construction progress

35% overall, as filed

Podiums0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Superstructure50%
Excavation100%
Basement & plinth100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

22 of 22 available
BuildingFloorTypeArea sq mAvailable
ALEKHYA ENCLAVE13BHK1862 of 2
ALEKHYA ENCLAVE13BHK1631 of 1
ALEKHYA ENCLAVE13BHK1581 of 1
ALEKHYA ENCLAVE23BHK1862 of 2
ALEKHYA ENCLAVE33BHK1861 of 1
ALEKHYA ENCLAVE33BHKmortgaged1863 of 3
ALEKHYA ENCLAVE33BHKmortgaged1631 of 1
ALEKHYA ENCLAVE43BHK1862 of 2
ALEKHYA ENCLAVE53BHK1864 of 4
ALEKHYA ENCLAVE63BHK1864 of 4
ALEKHYA ENCLAVE63BHK1631 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

ALEKHYA CONSTRUCTIONS LIMITED

CompanyPromoter type
Hyderabad, TelanganaBased in
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
RAI DURGA
Village
Rai Darga
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500032
North boundary
ROAD WIDTH - 12
East boundary
OTHERS LAND
South boundary
OTHERS LAND
West boundary
OTHERS LAND
What’s nearby
Schools2 schools within 500m · 4 educational institutions within 1km · College or university 1.7km away
HealthcareHospital 547m away · 3 clinics within 1km · Pharmacy within 1km
LifestylePark 689m away · Gym or sports centre 1.3km away · 17+ restaurants and cafes within 1km
ShoppingSupermarket 260m away · Mall 1.1km away · Bank 622m away
Getting around
Expressway 4.1 kmPrimary road 556 m · Shaikpet FlyoverMetro station 2.9km away (Peddamma Gudi)Bus stop within 1km
Water & environment
Water body 1.2 km · Shaikpet Cheruvu
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 1/C20/00250/2022Survey no. 10, 11
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1/C20/00250/2022 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.