HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
10 × 3BHK
Saleable area
156–159 sq mper unit, as filed
Floors
5
Land area
555 sq m
Built-up area
1,397 sq m

Timeline

RERA approvedNov 2024
Proposed completionNov 2027
TodayJul 2026
Construction progress

17.5% overall, as filed

Basement & plinth0%
Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Internal finishes10%
Stairs & lifts15%
Superstructure20%
Stilt floor30%
Excavation100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

10 of 10 available
BuildingFloorTypeArea sq mAvailable
AMAYA BLOCK - A13BHKmortgaged1561 of 1
AMAYA BLOCK - A13BHKmortgaged1591 of 1
AMAYA BLOCK - A23BHK1561 of 1
AMAYA BLOCK - A23BHK1591 of 1
AMAYA BLOCK - A33BHK1561 of 1
AMAYA BLOCK - A33BHK1591 of 1
AMAYA BLOCK - A43BHK1561 of 1
AMAYA BLOCK - A43BHK1591 of 1
AMAYA BLOCK - A53BHK1561 of 1
AMAYA BLOCK - A53BHK1591 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

AMBROSIA INDIA VENTURES LLP AND OTHER

LLPPromoter type
Hyderabad, TelanganaBased in
2Projects
1City
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
70 homeson the public record across 2 projects
11,767 sq mbuilt-up filed
4,551 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
MEDCHAL MALKAJGIRI DISTRICT
Village
Gundlapochampally
Mandal
Medchal
District
Medchal-Malkajgiri
Pincode
500100
North boundary
PLOT OF OTHERS
East boundary
30 FEET EXISTING ROAD
South boundary
PLOT OF OTHERS
West boundary
OTHERS LAND
What’s nearby
Schools2 schools within 1km
HealthcareNearest hospital 3.0km away · Doctor's clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 49m away
Getting around
Expressway 1.4 kmPrimary road 2.2 km · Medak RoadRailway line 741 mRailway station 845m away (Gundla Pochampally)Bus stop within 500m
Water & environment
Water body 235 m
distances only — not a flood assessment
Declared external development
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
Roads0%
Water supply0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit no. 0035/BP/3140/2024Survey no. SY NO 132 PART
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 0035/BP/3140/2024 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.