Complete project overview

RERA Telangana · Registration filing
Units
25 units
Unit mix
15 × 2BHK, 10 × 3BHK
Saleable area
118–144 sq mper unit, as filed
Floors
5
Land area
1,505 sq m
Built-up area
3,164 sq m

Timeline

RERA approvedSep 2022
Proposed completionSep 2025
TodayJul 2026
Construction progress

10% overall, as filed

Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Excavation100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

25 of 25 available
BuildingFloorTypeArea sq mAvailable
AMITY AVENUE13BHK1442 of 2
AMITY AVENUE12BHK1182 of 2
AMITY AVENUE12BHK1201 of 1
AMITY AVENUE23BHKmortgaged1441 of 1
AMITY AVENUE22BHKmortgaged1181 of 1
AMITY AVENUE22BHKmortgaged1201 of 1
AMITY AVENUE22BHK1181 of 1
AMITY AVENUE23BHK1441 of 1
AMITY AVENUE33BHK1442 of 2
AMITY AVENUE32BHK1182 of 2
AMITY AVENUE32BHK1201 of 1
AMITY AVENUE43BHK1442 of 2
AMITY AVENUE42BHK1182 of 2
AMITY AVENUE42BHK1201 of 1
AMITY AVENUE53BHK1442 of 2
AMITY AVENUE52BHK1182 of 2
AMITY AVENUE52BHK1201 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

TRI STRA BUILDERS & DEVELOPERS

PartnershipPromoter type
Medchal-Malkajgiri, TelanganaBased in
2Projects
2Cities
2022–2026Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
75 homeson the public record across 2 projects
9,580 sq mbuilt-up filed
3,933 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
SIDDIPET
Village
MITTAPALLY
Mandal
SIDDIPET (URBAN)
District
Siddipet
Pincode
502103
North boundary
NEIGHBORS PROPERTY
East boundary
FUNCTIONAL HALL
South boundary
60FT WIDE ROAD
West boundary
18FT COMMON PASSAGE
What’s nearby
Schools1 school within 1km · 3 educational institutions within 1km · College or university 953m away
HealthcareHospital 734m away · Clinic within 2km
LifestylePark 657m away · Gym or sports centre 1.5km away
ShoppingSupermarket 1.5km away · Mall 1.3km away · Bank 766m away
Getting around
Expressway 1.1 kmPrimary road 660 mRailway line 2.1 km · Manoharabad - Kothapalli new railway lineNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 757 m
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan
Building Permit no. 0032/BP/3056/2022Survey no. 1O45/A/LU

The promised possession date (26 Sep 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 0032/BP/3056/2022 on the approving authority’s portal to confirm the sanction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.