Complete project overview

RERA Telangana · Registration filing
Units
5 units
Unit mix
5 × Commercial Block
Saleable area
1222–1224 sq mper unit, as filed
Floors
4
Land area
2,844 sq m
Built-up area
6,091 sq m

Timeline

RERA approvedJun 2022
Proposed completionDec 2025
TodayJul 2026
Construction progress

57% overall, as filed

Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Internal finishes70%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Stairs & lifts100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

5 of 5 available
BuildingFloorTypeArea sq mAvailable
Amrutha Signature Towers1Commercial Block1,2241 of 1
Amrutha Signature Towers1Commercial Blockmortgaged1,2241 of 1
Amrutha Signature Towers2Commercial Block1,2221 of 1
Amrutha Signature Towers3Commercial Block1,2221 of 1
Amrutha Signature Towers4Commercial Block1,2221 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

AMRUTHA PROJECTS

PartnershipPromoter type
Hyderabad, TelanganaBased in
6Projects
1City
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
790 homeson the public record across 6 projects
1,35,006 sq mbuilt-up filed
42,554 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Next to Dhola-ri-Dhani, Kompally
Mandal
Dundigal Gandimaisamma
District
Medchal-Malkajgiri
Pincode
500014
North boundary
Neighbours Land
East boundary
Neighbours Land
South boundary
Land of Dr I Bhagwan Raju and Others
West boundary
National Highway No 44
What’s nearby
Schools1 school within 500m
HealthcareHospital 1.1km away · 2 clinics within 1km
LifestyleNo parks within 2km · 4 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Bank 836m away
Getting around
Expressway 234 m · Nizamabad RoadPrimary road 3.3 kmRailway line 968 mRailway station 2.7km away (Bolarum)Bus stop within 500m
Water & environment
Water body 651 m
distances only — not a flood assessment
Declared external development
Water supply100%
Roads0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit no. 003011/BP/HMDA/0540/MED/ 2022Survey no. Survey No 91/P

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 003011/BP/HMDA/0540/MED/ 2022 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.