Complete project overview

RAJ-RERA · Registration filing
Plots
160 plots
Land area
17,500 sq m
Completion deadline extended
3 extensions on record — latest to 7 Nov 2024declared reason: other than force majeure
Description
1.This project is plotted development consisting of residential plot. The Estimated finish date of the project was extended for the period of 1 year on 07-05-2020, the earlier finish date of the project is 31-03-2020, this bears the approval of honorable chairman. 2. Land Cost and Development cost of the project has updated on 02-09-2020. This bears the approval of Honorable Chairman Sir.

Timeline

RERA registeredApr 2018
Construction startApr 2018
Proposed completionMar 2020
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

160 plots across 33 batches
TypeArea sq mCount
Plot451
Plot5612
Plot721
Plot481
Plot671
Plot511
Plot552
Plot501
Plot541
Plot511
Plot531
Plot515
Plot531
Plot511
Plot511
Plot531
Plot531
Plot5283
Plot536
Plot5216
Plot521
Plot521
Plot531
Plot521
Plot521
Plot521
Plot521
Plot531
Plot521
Plot531
Plot5210
Plot6011
Plot3051

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

SWARNDHARA HOUSING LLP

OrganisationPromoter type
Alwar, RajasthanBased in
2Projects
1City
2018–2023Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
300 homes · 160 plotson the public record across 2 projects
13,624 sq mbuilt-up filed
17,500 sq mplotted area
32,767 sq mland declared
₹24.66 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Khasra No. 83,84 & 85, Huseengpur, Tapukara, Tijara, Alwar, 301018
Village
Tapukara
Taluka
Tijara
District
Alwar
Pincode
301018
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.8km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 577 mRailway line 810 m · Western Dedicated Freight CorridorNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 4.5 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹2.80 Cr declared to build 160 plots. What that works out to:

₹1.75 Lakhdeclared cost per plotall-in — land + construction
₹149/sq ftof plotted area₹1,600/sq m
73%of the cost is land₹109/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Bhiwadi Integrated Development Authority

Development Authority
Layout Permitapproved 6 Apr 2018 · 8 yrs ago

The promised possession date (31 Mar 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Bhiwadi Integrated Development Authority

Development authority

Has approved 59 RERA projects2.7% of Rajasthan.

an apartments market76% apartments · 24% plotted layouts. Layouts like yours are the smaller share here — this body mostly approves apartments.

Builders
39
On record
8,825 flats · 1,721 plots
Since
2017

More apartment-heavy than Rajasthan overall — 76% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.