01
Complete project overview
ORERA · Registration filing- Units
- 150 units
- Carpet area
- 21–72 sq mper-unit range, as filed
- Building type
- Apartment/Tower
- Parking
- 82 spaces
- Land area
- 2,815 sq m
- Plan valid until
- 15 Apr 2028
- Amenities
- 11 filed — Elecricity Supply, Water Supply, Plantation Area/No., Fire Fighting Facility, Internal Road, Gate Installation …
- Description
- B+S+5 Storied Residential Apartment Building
Timeline
Construction startSep 2027
Proposed completionMar 2030
UnitTypeCarpet sq m
B-101First Floor—36
B-102First Floor—36
B-103First Floor—36
B-104First Floor—36
B-105First Floor—36
B-106First Floor—36
B-107First Floor—21
B-108First Floor—21
B-109First Floor—21
B-110First Floor—21
B-111First Floor—21
B-112First Floor—21
B-113First Floor—21
B-114First Floor—36
B-115First Floor—36
B-116First Floor—36
B-117First Floor—36
B-118First Floor—36
B-119First Floor—36
B-120First Floor—36
B-121First Floor—21
B-122First Floor—21
B-123First Floor—21
B-124First Floor—21
B-125First Floor—21
B-126First Floor—21
B-127First Floor—36
B-128First Floor—36
B-129First Floor—36
B-130First Floor—72
B-201Second Floor—36
B-202Second Floor—36
B-203Second Floor—36
B-204Second Floor—36
B-205Second Floor—36
B-206Second Floor—36
B-207Second Floor—21
B-208Second Floor—21
B-209Second Floor—21
B-210Second Floor—21
B-211Second Floor—21
B-212Second Floor—21
B-213Second Floor—21
B-214Second Floor—36
B-215Second Floor—36
B-216Second Floor—36
B-217Second Floor—36
B-218Second Floor—36
B-219Second Floor—36
B-220Second Floor—36
B-221Second Floor—21
B-222Second Floor—21
B-223Second Floor—21
B-224Second Floor—21
B-225Second Floor—21
B-226Second Floor—21
B-227Second Floor—36
B-228Second Floor—36
B-229Second Floor—36
B-230Second Floor—72
B-301Third Floor—36
B-302Third Floor—36
B-303Third Floor—36
B-304Third Floor—36
B-305Third Floor—36
B-306Third Floor—36
B-307Third Floor—21
B-308Third Floor—21
B-309Third Floor—21
B-310Third Floor—21
B-311Third Floor—21
B-312Third Floor—21
B-313Third Floor—21
B-314Third Floor—36
B-315Third Floor—36
B-316Third Floor—36
B-317Third Floor—36
B-318Third Floor—36
B-319Third Floor—36
B-320Third Floor—36
B-321Third Floor—21
B-322Third Floor—21
B-323Third Floor—21
B-324Third Floor—21
B-325Third Floor—21
B-326Third Floor—21
B-327Third Floor—36
B-328Third Floor—36
B-329Third Floor—36
B-330Third Floor—72
B-401Fourth Floor—36
B-402Fourth Floor—36
B-403Fourth Floor—36
B-404Fourth Floor—36
B-405Fourth Floor—36
B-406Fourth Floor—36
B-407Fourth Floor—21
B-408Fourth Floor—21
B-409Fourth Floor—21
B-410Fourth Floor—21
B-411Fourth Floor—21
B-412Fourth Floor—21
B-413Fourth Floor—21
B-414Fourth Floor—36
B-415Fourth Floor—36
B-416Fourth Floor—36
B-417Fourth Floor—36
B-418Fourth Floor—36
B-419Fourth Floor—36
B-420Fourth Floor—36
B-421Fourth Floor—21
B-422Fourth Floor—21
B-423Fourth Floor—21
B-424Fourth Floor—21
B-425Fourth Floor—21
B-426Fourth Floor—21
B-427Fourth Floor—36
B-428Fourth Floor—36
B-429Fourth Floor—36
B-430Fourth Floor—72
B-501Fifth Floor—36
B-502Fifth Floor—36
B-503Fifth Floor—36
B-504Fifth Floor—36
B-505Fifth Floor—36
B-506Fifth Floor—36
B-507Fifth Floor—21
B-508Fifth Floor—21
B-509Fifth Floor—21
B-510Fifth Floor—21
B-511Fifth Floor—21
B-512Fifth Floor—21
B-513Fifth Floor—21
B-514Fifth Floor—36
B-515Fifth Floor—36
B-516Fifth Floor—36
B-517Fifth Floor—36
B-518Fifth Floor—36
B-519Fifth Floor—36
B-520Fifth Floor—36
B-521Fifth Floor—21
B-522Fifth Floor—21
B-523Fifth Floor—21
B-524Fifth Floor—21
B-525Fifth Floor—21
B-526Fifth Floor—21
B-527Fifth Floor—36
B-528Fifth Floor—36
B-529Fifth Floor—36
B-530Fifth Floor—72
Complete project overview — done
02
Builder’s track record
ORERA · Promoter registrationPrabhukrupa Realties Private Limited
Private Limited CompanyPromoter type
Puri, OdishaBased in
5Projects
2Cities
Timelineevery project, start → promised completion
20252026202720282029203020312032today
Builder DNAthe whole portfolio, summed
599 homeson the public record across 5 projects
20,919 sq mbuilt-up filed
13,632 sq mland declared
Planning authoritiesthis builder's portfolio, by approving body
Puri Konark Development AuthorityUrban Development Authoritythis project4 of 5 projects
Bhubaneswar Municipal CorporationMunicipal / Corporation1 of 5 projects
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Builder's track record — done
03
Location
ORERA · Registration filing- District
- Puri
- Town
- Puri
- Locality
- Samanga
- Pincode
- 752001
What’s nearbySchoolsNo schools within 2km
HealthcareNearest hospital 2.3km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting aroundExpressway 1.2 km · Marine Drive RoadPrimary road 2.0 km · Grand RoadRailway line 3.8 kmRailway station 3.8km away (Puri)Limited bus connectivity nearby
Water & environmentWater body 457 mRiver 1.6 km · Dhaudia River
distances only — not a flood assessment Land, title & encumbranceLand parcels4 parcels · 7,406 sq m total
Land tenure4 of 4 parcels held under a Power of Attorney / development agreement — not a registered sale deed to the promoter
VillageSamanga
Land classificationHomestead (Gharabari)
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict. Location — done
04
Planning authority
ORERA · Approved building planPuri Konark Development Authority
Urban Development AuthorityBuilding Permit
The occupancy certificate — the proof that isn’t hereA sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
The approving body, at scale
Puri Konark Development Authority
Development AuthorityHas approved 36 RERA projects — 3% of Odisha.
an apartments market — 92% apartments · 8% plotted layouts. Apartments like yours are this body's core business.
- Builders
- 26
- On record
- 3,854 flats · 114 plots
- Reach
- 6 pincodes
- Since
- 2019
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
Planning authority — done
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — ORERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — ORERA does not publish a complaints register. This read cannot speak to them either way.