HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
10 × 3BHK
Saleable area
141–145 sq mper unit, as filed
Floors
5
Land area
525 sq m
Built-up area
1,225 sq m

Timeline

RERA approvedAug 2019
Proposed completionAug 2025
TodayJul 2026
Construction progress

100% overall, as filed

Excavation100%
Basement & plinth100%
Podiums100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

10 of 10 available
BuildingFloorTypeArea sq mAvailable
ANMOL RAAGA13BHK1411 of 1
ANMOL RAAGA13BHK1451 of 1
ANMOL RAAGA23BHKmortgaged1411 of 1
ANMOL RAAGA23BHKmortgaged1451 of 1
ANMOL RAAGA33BHK1411 of 1
ANMOL RAAGA33BHK1451 of 1
ANMOL RAAGA43BHK1411 of 1
ANMOL RAAGA43BHK1451 of 1
ANMOL RAAGA53BHK1411 of 1
ANMOL RAAGA53BHK1451 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

ANMOL CONSTRUCTIONS DEVELOPERS AND INFRA

PartnershipPromoter type
Warangal Urban, TelanganaBased in
1Projects
1City
2019–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
SUBEDARI,NEAR EXCISE COLONY,HANAMKONDA,WARANGAL URBAN
Village
GMH Hanmakonda
Mandal
Hanamkonda
District
Warangal Urban
Pincode
506001
North boundary
EXISTING BUILDING
East boundary
9 M ROAD
South boundary
EXISTING BUILDING
West boundary
OPEN PLOT OF VENUGOPAL REDDY
What’s nearby
Schools1 school within 500m · 5 educational institutions within 1km · College or university 958m away
HealthcareHospital 383m away · Clinic within 2km · Pharmacy within 1km
LifestylePark 587m away · 4 restaurants and cafes within 1km · Swimming pool within 2km
ShoppingSupermarket 278m away · Mall 725m away · Convenience store within 500m
Getting around
Expressway 841 mPrimary road 841 mRailway line 2.9 kmRailway station 3.5km away (Kazipet Town)Bus stop within 500m
Water & environment
Canal 1.3 kmWater body 1.5 km
distances only — not a flood assessment
Declared external development
Roads100%
Water supply100%
Sewerage (Chamber,…100%
Rainwater100%
Green Strip/TOT LO…100%
Street lighting100%
Rainwater100%
Electricity100%
Aggregate area of …100%
Community Building…0%
Sewage0%
Solid waste0%
Renewable energy0%
Fire safety0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit

The promised possession date (16 Aug 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.