HORIZONMarkets
01

Complete project overview

UP-RERA · Registration filing
Units
208 units
Unit mix
112 × 4 BHK · 80 × 3 BHK · 16 × VILLA
Carpet area
95–334 sq mper unit, as filed
Floors
18
Blocks
5
Land area
20,233 sq m

Timeline

Project startedApr 2016
RERA registeredAug 2017
Proposed completionMar 2022
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

208 units across 113 batches
BuildingFloorTypeArea sq mCount
A13 BHK952
A14 BHK1192
A23 BHK952
A24 BHK1192
A33 BHK952
A34 BHK1192
A43 BHK952
A44 BHK1192
A53 BHK952
A54 BHK1192
A63 BHK952
A64 BHK1192
A73 BHK952
A74 BHK1192
A83 BHK952
A84 BHK1192
A93 BHK952
A94 BHK1192
A103 BHK952
A104 BHK1192
A113 BHK952
A114 BHK1192
A123 BHK952
A124 BHK1192
A133 BHK952
A134 BHK1192
A144 BHK1192
A143 BHK952
A153 BHK952
A154 BHK1192
A163 BHK952
A164 BHK1192
A173 BHK952
A174 BHK1192
A183 BHK952
A184 BHK1192
B13 BHK952
B14 BHK1192
B24 BHK1192
B23 BHK952
B33 BHK952
B34 BHK1192
B43 BHK952
B44 BHK1192
B53 BHK952
B54 BHK1192
B63 BHK952
B64 BHK1192
B73 BHK952
B74 BHK1192
B83 BHK952
B84 BHK1192
B93 BHK952
B94 BHK1192
B103 BHK952
B104 BHK1192
B113 BHK952
B114 BHK1192
B123 BHK952
B124 BHK1192
B133 BHK952
B134 BHK1192
B143 BHK952
B144 BHK1192
B153 BHK952
B154 BHK1192
B163 BHK952
B164 BHK1192
B173 BHK952
B174 BHK1192
B183 BHK952
B184 BHK1192
C13 BHK952
C14 BHK1192
C23 BHK952
C24 BHK1192
C34 BHK1191
C44 BHK1191
C54 BHK1191
C64 BHK1191
C74 BHK1191
C84 BHK1191
C94 BHK1191
C104 BHK1191
C114 BHK1191
C124 BHK1191
C134 BHK1191
C144 BHK1191
C154 BHK1191
C164 BHK1191
C174 BHK1191
C184 BHK1191
D13 BHK952
D14 BHK1192
D23 BHK952
D24 BHK1192
D34 BHK1191
D44 BHK1191
D54 BHK1191
D64 BHK1191
D74 BHK1191
D84 BHK1191
D94 BHK1191
D104 BHK1191
D114 BHK1191
D124 BHK1191
D134 BHK1191
D144 BHK1191
D154 BHK1191
D164 BHK1191
D174 BHK1191
D184 BHK1191
VillaGFVILLA33416

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

CONSORTIUM INFRASTRUCTURE PVT LTD (ANTRIKSH INDIA

CompanyPromoter type
1Registered projects
1Projects
1City
2017–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

UP-RERA · Registration filing
District
Gautam Buddha Nagar
Tehsil
Gautam Buddha Nagar
Site access
12 M WIDE ROAD ON TWO SIDES
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.9km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.0 km · Noida-Greater Noida ExpresswayMetro station 2.5km away (Noida Sector 148)Limited bus connectivity nearby
Water & environment
Water body 808 mRiver 1.0 km · Yamuna
distances only — not a flood assessment
04

Planning authority

UP-RERA · Approved building plan
approved 1 Nov 2013 · 12 yrs ago
Building Permit no. IV-1416

The promised possession date (31 Mar 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan IV-1416 on the approving authority’s portal to confirm the sanction.

Complaints register

2 complaints on UP-RERA’s register for this project.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.