Complete project overview

RERA Telangana · Registration filing
Units
15 units
Unit mix
10 × 2BHK, 5 × 3BHK
Saleable area
93–125 sq mper unit, as filed
Floors
5
Land area
724 sq m
Built-up area
2,285 sq m

Timeline

RERA approvedJul 2017
Proposed completionJul 2023
TodayJul 2026
Construction progress

27% overall, as filed

Podiums0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Stilt floor70%
Excavation100%
Basement & plinth100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

15 of 15 available
BuildingFloorTypeArea sq mAvailable
APPLE RIDGE12BHK931 of 1
APPLE RIDGE12BHK951 of 1
APPLE RIDGE13BHK1251 of 1
APPLE RIDGE22BHKmortgaged931 of 1
APPLE RIDGE22BHKmortgaged951 of 1
APPLE RIDGE23BHK1251 of 1
APPLE RIDGE32BHK931 of 1
APPLE RIDGE32BHK951 of 1
APPLE RIDGE33BHK1251 of 1
APPLE RIDGE42BHK931 of 1
APPLE RIDGE42BHK951 of 1
APPLE RIDGE43BHK1251 of 1
APPLE RIDGE52BHK931 of 1
APPLE RIDGE52BHK951 of 1
APPLE RIDGE53BHK1251 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

DHAMAM INFRA PROJECTS PRIVATE LIMITED

CompanyPromoter type
Ranga Reddy, TelanganaBased in
2Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
30 homeson the public record across 2 projects
3,640 sq mbuilt-up filed
1,198 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
JNTU Welfare society
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500049
North boundary
PLOT NO 5 PLOT NO 6 PLOT NO 7
East boundary
PLOT NO 14
South boundary
30 FT WIDE ROAD
West boundary
30 FT WIDE ROAD
What’s nearby
Schools1 school within 500m · 19 educational institutions within 1km · College or university 338m away
HealthcareHospital 212m away · 16 clinics within 1km · Pharmacy within 500m
LifestylePark 544m away · Playground within 500m · Gym or sports centre 202m away
ShoppingSupermarket 74m away · Mall 54m away · Convenience store within 500m
Getting around
Expressway 677 m · Nizampet - JNTU Road Mumbai HighwayPrimary road 98 m · JNTU RoadRailway line 2.1 kmMetro station 990m away (JNTU College)3 bus stops within 500m
Water & environment
Water body 864 m
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 1/C12/05965/2017Survey no. 44/1

The promised possession date (2 Jul 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1/C12/05965/2017 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.