01
Complete project overview
UP-RERA · Registration filing- Units
- 3,06,660 units
- Unit mix
- 229976 × 3 BHK · 76684 × 2 BHK
- Carpet area
- 57–87 sq mper unit, as filed
- Floors
- 19
- Blocks
- 2
- Land area
- 26,758 sq m
Timeline
Proposed completionSep 2021
BuildingFloorTypeArea sq mCount
R1-A13 BHK87203
R1-A12 BHK57207
R1-A13 BHK77211
R1-A13 BHK67215
R1-A23 BHK87403
R1-A22 BHK57407
R1-A23 BHK77411
R1-A23 BHK67415
R1-A33 BHK87603
R1-A32 BHK57607
R1-A33 BHK77611
R1-A33 BHK67615
R1-A43 BHK87803
R1-A42 BHK57807
R1-A43 BHK77811
R1-A43 BHK67815
R1-A53 BHK871,003
R1-A52 BHK571,007
R1-A53 BHK771,011
R1-A53 BHK671,015
R1-A63 BHK871,203
R1-A62 BHK571,207
R1-A63 BHK771,211
R1-A63 BHK671,215
R1-A73 BHK871,403
R1-A72 BHK571,407
R1-A73 BHK771,411
R1-A73 BHK671,415
R1-A83 BHK871,603
R1-A82 BHK571,607
R1-A83 BHK771,611
R1-A83 BHK671,615
R1-A93 BHK871,803
R1-A92 BHK571,807
R1-A93 BHK771,811
R1-A93 BHK671,815
R1-A103 BHK872,003
R1-A102 BHK572,007
R1-A103 BHK772,011
R1-A103 BHK672,015
R1-A113 BHK872,203
R1-A112 BHK572,207
R1-A113 BHK772,211
R1-A113 BHK672,215
R1-A123 BHK872,403
R1-A122 BHK572,407
R1-A123 BHK772,411
R1-A123 BHK672,415
R1-A133 BHK672,615
R1-A133 BHK872,603
R1-A132 BHK572,607
R1-A133 BHK772,611
R1-A143 BHK672,815
R1-A143 BHK872,803
R1-A142 BHK572,807
R1-A143 BHK771,405
R1-A143 BHK771,406
R1-A153 BHK673,015
R1-A153 BHK873,003
R1-A152 BHK573,007
R1-A153 BHK773,011
R1-A163 BHK673,215
R1-A163 BHK873,203
R1-A162 BHK573,207
R1-A163 BHK773,211
R1-A173 BHK673,415
R1-A173 BHK873,403
R1-A172 BHK573,407
R1-A173 BHK773,411
R1-A183 BHK673,615
R1-A183 BHK873,603
R1-A182 BHK573,607
R1-A183 BHK773,611
R1-A193 BHK673,815
R1-A193 BHK873,803
R1-A192 BHK573,807
R1-A193 BHK773,811
R1-B13 BHK87233
R1-B12 BHK57229
R1-B13 BHK77223
R1-B13 BHK67219
R1-B23 BHK87433
R1-B22 BHK57429
R1-B23 BHK77423
R1-B23 BHK67419
R1-B33 BHK87633
R1-B32 BHK57629
R1-B33 BHK77623
R1-B33 BHK67619
R1-B43 BHK87833
R1-B42 BHK57829
R1-B43 BHK77823
R1-B43 BHK67819
R1-B53 BHK871,033
R1-B52 BHK571,029
R1-B53 BHK771,023
R1-B53 BHK671,019
R1-B63 BHK871,233
R1-B62 BHK571,229
R1-B63 BHK771,223
R1-B63 BHK671,219
R1-B73 BHK871,433
R1-B72 BHK571,429
R1-B73 BHK771,423
R1-B73 BHK671,419
R1-B83 BHK871,633
R1-B82 BHK571,629
R1-B83 BHK771,623
R1-B83 BHK671,619
R1-B93 BHK871,833
R1-B92 BHK571,829
R1-B93 BHK771,823
R1-B93 BHK671,819
R1-B103 BHK872,033
R1-B102 BHK572,029
R1-B103 BHK772,023
R1-B103 BHK672,019
R1-B113 BHK871,116
R1-B112 BHK572,229
R1-B113 BHK772,223
R1-B113 BHK672,219
R1-B123 BHK872,433
R1-B122 BHK572,429
R1-B123 BHK772,423
R1-B123 BHK672,419
R1-B133 BHK872,633
R1-B132 BHK572,629
R1-B133 BHK772,623
R1-B133 BHK672,619
R1-B143 BHK872,833
R1-B142 BHK572,829
R1-B143 BHK772,823
R1-B143 BHK672,819
R1-B153 BHK873,033
R1-B152 BHK573,029
R1-B153 BHK773,023
R1-B153 BHK673,019
R1-B163 BHK873,233
R1-B162 BHK573,229
R1-B163 BHK771,611
R1-B163 BHK771,612
R1-B163 BHK673,219
R1-B173 BHK874,550
R1-B172 BHK573,429
R1-B173 BHK773,423
R1-B173 BHK673,419
R1-B183 BHK873,633
R1-B182 BHK573,629
R1-B183 BHK773,623
R1-B183 BHK673,619
R1-B193 BHK873,833
R1-B192 BHK573,829
R1-B193 BHK773,823
R1-B193 BHK673,819
Complete project overview — done
02
Builder’s track record
UP-RERA · Promoter registrationAROCON REAL ESTATE PVT. LTD.
CompanyPromoter type
1Registered projects
1Projects
1City
2018–2021Active
Timelineevery project, start → promised completion
201820192020202120222023202420252026today
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Builder's track record — done
03
Location & price analysis
UP-RERA · Registration filing- District
- Ghaziabad
- Tehsil
- Ghaziabad
- Site access
- 24M WIDE ROAD UPTO GATE OF PROJECT
What’s nearbySchoolsNo schools within 2km
HealthcareHospital 732m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting aroundExpressway 576 mRailway line 1.7 kmRailway station 4.7km away (Naya Ghaziabad)Limited bus connectivity nearby
Water & environmentWater body 702 mCanal 1.9 km
distances only — not a flood assessment Price analysisdeclared build cost — not a sale price
₹70.00 Cr declared to build 3,06,660 flats. What that works out to:
₹2,283declared cost per flatall-in — land + construction
Location & price analysis — done
04
Planning authority
UP-RERA · Approved building planapproved 29 Sep 2014 · 11 yrs ago
Building Permit no. 65/ZONE-5/2014-15
The promised possession date (30 Sep 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
Completion Certificate — the occupancy sign-off, on recordA Completion Certificateis on this project’s RERA record (dated 14 Dec 2023)— the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit before you rely on it.
Verify it yourself — look up plan 65/ZONE-5/2014-15 on the approving authority’s portal to confirm the sanction.
Planning authority — done
Complaints registerNone on record with UP-RERA against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.