Complete project overview

RAJ-RERA · Registration filing
Land area
6,400 sq m
Completion deadline extended
1 extension on record — latest to 28 Mar 2020declared reason: other than force majeure

Timeline

RERA registeredFeb 2018
Proposed completionJun 2019
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

HARMINDER SINGH ATWAL

IndividualPromoter type
Kota, RajasthanBased in
1Projects
1City
2018–2019Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
KHASRA NO.-380/232, ATWAL ENCLAVE,KOTRI, KOTRI IN, Ladpura, Kota, 324001
Village
KOTRI IN
Taluka
Ladpura
District
Kota
Pincode
324001
What’s nearby
SchoolsNearest school 1.9km away
HealthcareHospital 121m away · 7 clinics within 1km · Doctor's clinic within 1km
Lifestyle2 parks within 500m · 3 restaurants and cafes within 1km
ShoppingSupermarket 111m away
Getting around
Primary road 129 m · Chhawani FlyoverRailway line 1.6 km · Mumbai - Delhi RailwayRailway station 3.6km away (Dakaniya Talav)Limited bus connectivity nearby
Water & environment
Water body 90 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹5.48 Cr declared. What that works out to:

₹795/sq ftof plotted area₹8,563/sq m
64%of the cost is land₹505/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Urban Improvement Trust

Urban Improvement Trust
Layout Permitapproved 14 Feb 2018 · 8 yrs ago

The promised possession date (28 Jun 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Urban Improvement Trust

A city-level Urban Improvement Trust — Rajasthan's town-development body in cities without a development authority. It has approved 612 RERA projects across 20 districts about 1 in 4 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.