2 extensions on record — latest to 8 May 2025declared reason: other than force majeure
Description
12.5% of the total saleable plots has been mortgaged by the Jaipur Development Authority, Jaipur against the internal development work of the project those plots are plot no. 7 to 14, 16, to 20 and 45, 46 admeasuring 1608.82 Sq.M. (2). The Open Area of our project is 7410.88 Sq. Mtr. Calculated as (Park-985 Sq. Mtr.+Road 6425.88 Sq. Mtr.) 3). 12.5% of the total saleable plots has been released by the Jaipur Development Authority, Jaipur against the internal development work of the project those plots are plot no. 7 to 14, 16, to 20 and 45, 46 admeasuring 1608.82 Sq.M.
Timeline
Construction startJan 2024
RERA registeredJan 2024
Proposed completionMay 2024
TodaySep 2026
Find your plot
Filed by type and size, in the batches the builder registered — not a per-plot listing. Look yours up.
114 plots across 51 batches
TypeArea sq mCount
Plot903
Plot941
Plot1055
Plot871
Plot961
Plot1271
Plot9236
Plot1146
Plot1681
Plot961
Plot1241
Plot1351
Plot1021
Plot10510
Plot1611
Plot1009
Plot891
Plot1301
Plot3941
Plot1051
Plot1121
Plot821
Plot1071
Plot831
Plot811
Plot1701
Plot1131
Plot901
Plot901
Plot1171
Plot1591
Plot1111
Plot921
Plot971
Plot911
Plot1911
Plot1501
Plot921
Plot791
Plot1291
Plot1131
Plot1541
Plot951
Plot901
Plot841
Plot1691
Plot1261
Plot851
Plot861
Plot1491
Plot1301
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).
The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Expressway 4.7 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Canal 2.0 kmWater body 2.5 km · Nevta Lake
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price
₹7.83 Cr declared to build 114 plots. What that works out to:
₹6.87 Lakhdeclared cost per plotall-in — land + construction
₹369/sq ftof plotted area₹3,975/sq m
81%of the cost is land₹299/sq ft of land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Rajasthan IGRS — DLC rates
In Rajasthan it’s called the DLC rate.
₹7,525per sq yd
₹9,000per sq m
Which rate
residential, interior plot
Matched to
The rate published for the village of “PEEPLA BHARATSINGH”.
Highest rate
₹23,077 per sq yd — the top road-facing rate among the 5 residential rates published for this village
By the road it faces
interior plot
₹9,000 / sq m
₹7,525 / sq yd
road-facing
₹13,100 / sq m
₹10,953 / sq yd
41–60 ft road
₹14,410 / sq m
₹12,049 / sq yd
61–99 ft road
₹15,070 / sq m
₹12,600 / sq yd
100 ft+ road
₹15,720 / sq m
₹13,144 / sq yd
The same land, priced by the width of the road it faces — each band the middle of the residential rates published for this village.
This filing declares ₹3,975 per sq m of plotted area — 0.44× the government figure. Declared cost is land and construction; the government guidance rate is what the state will not register a sale below. Neither is a sale price.
What this number is — and isn’t
The minimum value Rajasthan’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
Not a market price. Sales normally register above it, and how far above varies by place and by project.
Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
Government Guidance Rate — done
05
Planning authority
RAJ-RERA · Approved building plan
Layout Permitapproved 29 Jan 2024 · 2 yrs ago
The promised possession date (8 May 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
Planning authority — done
06
Complaints & litigation
RAJ-RERA · public record
Complaints register
Not published. RAJ-RERA doesn’t publish a complaints register in the record Horizon reads.
So there is nothing to count here — which is not the same as nothing having been filed.
What the builder declared
Declared to RAJ-RERA
Litigation
None declared in this filing
Only what the builder declared, or what RAJ-RERA records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RAJ-RERA, or that this register doesn’t publish it — never that nothing happened.