RERA Telangana · Registration filing
Units
48 units
Unit mix
47 × 3BHK, 1 × 3bh
Saleable area
148–153 sq mper unit, as filed
Floors
6
Land area
2,340 sq m
Built-up area
6,680 sq m

Timeline

RERA approvedMay 2021
Proposed completionMay 2027
TodayJul 2026
Construction progress

41.5% overall, as filed

Podiums0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal finishes40%
Superstructure75%
Excavation100%
Basement & plinth100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

48 of 48 available
BuildingFloorTypeArea sq mAvailable
AYATI HILL TOP13BHKmortgaged1537 of 7
AYATI HILL TOP13BHK1531 of 1
AYATI HILL TOP23BHK1538 of 8
AYATI HILL TOP33BHK1536 of 6
AYATI HILL TOP33bh1531 of 1
AYATI HILL TOP33BHK1481 of 1
AYATI HILL TOP43BHK1488 of 8
AYATI HILL TOP53BHK1488 of 8
AYATI HILL TOP63BHK1488 of 8

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

AYATI PROPERTIES

PartnershipPromoter type
Hyderabad, TelanganaBased in
5Projects
1City
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
108 homeson the public record across 5 projects
12,874 sq mbuilt-up filed
5,345 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
BANDLAGUDA JAGIR
District
Ranga Reddy
Pincode
500086
North boundary
PLOT NO 243 AND 244 AND 245
East boundary
30 FEET WIDE ROAD
South boundary
PLOT NO 240 AND 248
West boundary
40 FEET WIDE ROAD
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.1km away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingSupermarket 944m away · Bank 761m away
Getting around
Expressway 365 m · Chavella roadPrimary road 2.6 kmNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 78 m · Peeran Cheruvu
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 24 IN PART NO 26 AND 27
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.