Complete project overview

WBRERA · Registration filing
Apartments
16
Land area
744 sq m
Built-up area
1,521 sq m
Carpet area
1,228 sq m
Parking
16 spaces
RERA registered
2023

Timeline

RERA registeredJan 2023
Proposed completionDec 2024
TodayJul 2026
02

Builder’s track record

WBRERA · Promoter registration

Bhumi & Co.

Partnership FirmPromoter type
West Midnapore, West BengalBased in
1Projects
1City
2023–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

WBRERA · Registration filing
District
West Midnapore
Municipality / area
Kharagpur Municipality
Police station
Kharagpur Town
Address
Holding No. 225/190, INDA, KHARAGPUR NA
Pincode
721305
What’s nearby
SchoolsNo schools within 2km · College or university 602m away
HealthcareHospital 2.0km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Mall 270m away
Getting around
Expressway 2.1 kmPrimary road 237 m · Kharagpur City RoadRailway line 676 mRailway station 1.7km away (Kharagpur Junction)Limited bus connectivity nearby
Water & environment
Water body 183 mRiver 4.8 km · Kangsabati
distances only — not a flood assessment
04

Planning authority

WBRERA · Approved building plan

Kharagpur Municipality

Municipality
Building Permit no. SWS-OBPAS/1603/2022/0072

The promised possession date (31 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan SWS-OBPAS/1603/2022/0072 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kharagpur Municipality

Municipal corporation / municipality

Has approved 22 RERA projects0.9% of West Bengal.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
19
On record
733 flats · 0 plots

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — WBRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — WBRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — WBRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.