HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
16 units
Unit mix
16 × 4BHK
Saleable area
418 sq mper unit, as filed
Floors
1
Buildings
16
Land area
7,487 sq m
Built-up area
11,925 sq m
Road widening
1,142 sq mland set aside for road widening

Timeline

RERA approvedSep 2021
Proposed completionNov 2025
TodayJul 2026
Construction progress

12.5% overall, as filed

Basement & plinth0%
Podiums0%
Stilt floor0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Superstructure25%
Excavation100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

14 of 16 available
BuildingFloorTypeArea sq mAvailable
VILLA 114BHKmortgaged4181 of 1
VILLA 1014BHK4181 of 1
VILLA 1114BHK4180 of 1
VILLA 1214BHK4181 of 1
VILLA 1314BHK4181 of 1
VILLA 1414BHK4181 of 1
VILLA 1514BHK4181 of 1
VILLA 1614BHK4181 of 1
VILLA 214BHKmortgaged4181 of 1
VILLA 314BHK4180 of 1
VILLA 414BHK4181 of 1
VILLA 514BHK4181 of 1
VILLA 614BHK4181 of 1
VILLA 714BHK4181 of 1
VILLA 814BHK4181 of 1
VILLA 914BHK4181 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

MARK NIRMAAN

PartnershipPromoter type
Hyderabad, TelanganaBased in
1Projects
1City
2021–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Telangana · Registration filing
Locality
AIRPORT ROAD
Village
Balapur
Mandal
Balapur
District
Ranga Reddy
Pincode
500005
North boundary
NEIGHBOURS LAND
East boundary
ROAD TO KURMALGUDA VILLAGE
South boundary
LAND OF PUNA SATTAIAH AND PUNA PRAMILLA
West boundary
NEIGHBOURS LAND
What’s nearby
SchoolsNo schools within 2km · College or university 2.0km away
HealthcareHospital 1.3km away
LifestylePark 1.5km away
ShoppingSupermarket 1.5km away
Getting around
Expressway 2.0 km · Srisailam HighwayPrimary road 3.1 km · Inner Ring RoadRailway line 3.4 kmRailway station 3.9km away (Budvel)Limited bus connectivity nearby
Water & environment
Water body 1.4 km
distances only — not a flood assessment
Government land classification

Land here includes House Sites (residential), plus Dry land, Wet Land double crop, Agricultural Land fit for H.S.. The state classes land per survey— confirm your plot’s survey number is House Sites.

Telangana Registration & Stamps
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisno declared cost on this filing — one government benchmark below

This state’s RERA filing carries no declared build cost at all — nothing to turn into a per-unit or per-sq-ft figure here. The one real, government-sourced number below is the closest thing to a benchmark this record can offer.

Government guidance value
₹2,000/sq ydHouse Sites

₹2,392/sq m · effective Jan 2013

The state’s minimum value for this village’s land, set for stamp duty — a floor, not a market price. Source: Telangana Registration & Stamps.

04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit no. 000325/LO/Plg/HMDA/2021Survey no. 80/7

The promised possession date (21 Nov 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 000325/LO/Plg/HMDA/2021 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.