HORIZONMarkets
01

Complete project overview

RERA Andhra Pradesh · Registration filing
Units
30 flats
Unit mix
25 × 2BHK · 5 × 3BHK
Carpet area
63–81 sq m
Floors
5
Land area
873 sq m
Built-up area
3,500 sq m

Timeline

Project startedJun 2023
RERA approvedSep 2023
Proposed completionJan 2025
TodayJul 2026

Find your flat

Every flat the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitTypeCarpet sq mBalcony sq mOuter wall sq mCommon sq mTotal sq mParking sq m
1011st Floor · 13BHK81.366.618.9925.20122.1610
1021st Floor · 12BHK75.697.598.2823.63115.1910
1031st Floor · 12BHK72.657.948.4723.34112.4010
1041st Floor · 12BHK62.6517.877.7923.17111.4810
1051st Floor · 12BHK79.488.617.9524.73120.7710
1061st Floor · 12BHK76.788.718.0424.45117.9810
2012nd Floor · 13BHK81.366.618.9925.20122.1610
2022nd Floor · 12BHK75.697.598.2823.63115.1910
2032nd Floor · 12BHK72.657.948.4723.34112.4010
2042nd Floor · 12BHK62.6517.877.7923.17111.4810
2052nd Floor · 12BHK79.488.617.9524.73120.7710
2062nd Floor · 12BHK76.788.718.0424.45117.9810
3013rd Floor · 13BHK81.366.618.9925.20122.1610
3023rd Floor · 12BHK75.697.598.2823.63115.1910
3033rd Floor · 12BHK72.657.948.4723.34112.4010
3043rd Floor · 12BHK62.6517.877.7923.17111.4810
3053rd Floor · 12BHK79.488.617.9524.73120.7710
3063rd Floor · 12BHK76.788.718.0424.45117.9810
4014th Floor · 13BHK81.366.618.9925.20122.1610
4024th Floor · 12BHK75.697.598.2823.63115.1910
4034th Floor · 12BHK72.657.948.4723.34112.4010
4044th Floor · 12BHK62.6517.877.7923.17111.4810
4054th Floor · 12BHK79.488.617.9524.73120.7710
4064th Floor · 12BHK76.788.718.0424.45117.9810
5015th Floor · 13BHK81.366.618.9925.20122.1610
5025th Floor · 12BHK75.697.598.2823.63115.1910
5035th Floor · 12BHK72.657.948.4723.34112.4010
5045th Floor · 12BHK62.6517.877.7923.17111.4810
5055th Floor · 12BHK79.488.617.9524.73120.7710
5065th Floor · 12BHK76.788.718.0424.45117.9810

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. Carpet area is the legally meaningful number — not the super built-up figure a brochure quotes.

02

Builder’s track record

RERA Andhra Pradesh · Promoter registration

DHRITI CONSTRUCTIONS

Partnership/LLP FirmPromoter type
Y.S.R KadapaBased in
2Projects
2Cities
2019–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
45 homeson the public record across 2 projects
4,810 sq mbuilt-up filed
1,371 sq mland declared
₹9.23 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Director, Town and Country PlanningTown & Country Planning (DTCP)this project1 of 2 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Andhra Pradesh · Registration filing
Village
RAJAMPET
Mandal
Rajampet
District
Y.S.R Kadapa
Pincode
516115
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 59m away · 3 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 326m away
Getting around
Expressway 765 mPrimary road 539 m · Rayachoti-Rajampet roadRailway line 1.2 kmRailway station 1.3km away (Razampet)Bus stop within 500m
Water & environment
River 1.0 km · Pullageru RiverWater body 1.9 km
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewage0%
Electricity0%
Solid waste0%
Fire safety0%
Water0%
Emergency exits0%
Renewable energy0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisdeclared build cost — not a sale price

₹9.23 Cr declared to build 30 flats. What that works out to:

₹30.76 Lakhdeclared cost per flatall-in — land + construction
₹2,450/sq ftof built-up area₹26,367/sq m
5%of the cost is land₹485/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Andhra Pradesh · Approved building plan

Director, Town and Country Planning

Town & Country Planning (DTCP) · RAJAMPET
approved 5 Jan 2021 · 5 yrs ago
Building Permit no. 1120/0187/B/RJP MPL/BPRA/2021Survey no. 841

The promised possession date (5 Jan 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1120/0187/B/RJP MPL/BPRA/2021 on the approving authority’s portal (dtcp.ap.gov.in) to confirm the sanction.

The approving body, at scale

Director, Town & Country Planning (DTCP)

Andhra Pradesh's statewide town-planning directorate. It has approved 1,597 RERA projects across 13 mandals about 1 in 4 in Andhra Pradesh.

This project sits in its RAJAMPET area — a smaller local market, with too few RERA projects on record to profile on its own.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Andhra Pradesh does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Andhra Pradesh does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — RERA Andhra Pradesh does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.