Registration lapsed

This project’s RERA Assam registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with RERA Assam before you rely on anything below.

01

Complete project overview

RERA Assam · Registration filing
Registration category
ONGOINGnew vs ongoing at registration
Land area
4,434 sq m
Local land measure
3 Bigha 1 katha 11.5 lecha
RERA validity
31 Dec 2022this validity has passed

Timeline

RERA registeredJul 2017
Proposed completionDec 2022
TodayJul 2026
Construction progress

0% overall, as filed

Self-declared % complete as filed with RERA Assam when this ongoing project was registered — a snapshot at registration, not a live tracker.
02

Builder’s track record

RERA Assam · Promoter registration

M/S NEW EAST INFRA HOLDINGS PVT. LTD.

CompanyPromoter type
1Projects
1City
2017–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Assam · Registration filing
District
JORHAT
Mouza / circle
JORHAT EAST
Town / village
Jorhat
Site address
CITY CENTER MALL, NEAR MAHENDRA SHOWROOM BORPUL, KENDUGURI, A.T. ROAD, JORHAT, ASSAM- 785010
Pincode
785010
What’s nearby
SchoolsNo schools within 2km · College or university 2.0km away
HealthcareNearest hospital 2.0km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Mall 2.0km away
Getting around
Expressway 1.3 kmPrimary road 1.9 km · Mahatma Gandhi RoadRailway line 1.1 kmRailway station 2.1km away (Jorhat Town)Limited bus connectivity nearby
Water & environment
River 988 m · Bhogdoi RiverWater body 1.7 km
distances only — not a flood assessment
04

Planning authority

RERA Assam · Approved building plan

Jorhat Development Authority

Urban Development Authority
Building Permitapproved 23 Aug 2016 · 9 yrs ago

The promised possession date (31 Dec 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jorhat Development Authority

Development authority

Has approved 17 RERA projects1.9% of Assam.

an apartments market94% apartments · 6% plotted layouts. Apartments like yours are this body's core business.

Builders
16
On record
221 flats · 2,295 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Assam does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Assam does not publish a complaints register. This read cannot speak to them either way.