Complete project overview

UP-RERA · Registration filing
Land area
21,509 sq m

Timeline

RERA registeredSep 2017
Project startedNov 2017
Proposed completionDec 2023
TodayJul 2026
02

Builder’s track record

UP-RERA · Promoter registration

LUXMI INFRA HOMES PRIVATE LIMITED

CompanyPromoter type
1Registered projects
1Projects
1City
2017–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Hapur
Site access
528, MEERAPUR ROAD, PILKHUWA, HAPUR
What’s nearby
SchoolsNo schools within 2km · Library 272m away
HealthcareHospital 280m away · 6 clinics within 1km · Pharmacy within 500m
Lifestyle2 parks within 500m · Gym or sports centre 1.2km away · Swimming pool within 2km
ShoppingNo supermarket within 2km · Bank 245m away
Getting around
Expressway 2.7 kmPrimary road 2 m · Merrut-Bulandsehar RoadRailway line 874 mRailway station 1.0km away (Hapur Junction)Bus stop within 500m
Water & environment
River 2.5 kmWater body 4.9 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹25.00 Cr declared. What that works out to:

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 25 May 2016 · 10 yrs ago
Building Permit no. 58/14-15/L/PKW

The promised possession date (29 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 58/14-15/L/PKW on the approving authority’s portal to confirm the sanction.

Complaints register

None on record with UP-RERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.