Complete project overview
HRERA Gurugram · Registration filing- Units
- 544 units
- Land area
- 42,846 sq m
- Parking
- 1,482 spaces
- Statutory approvals
- 4 declared obtained · Building, Height, Aravali, Forestclearances the promoter declared obtained at registration — not independently verified here
- Revised completion
- 30 Jun 2021revised completion date the promoter filed with HRERA — later than the original
Timeline
20% overall, as filed
The % of external / site infrastructure (roads, water, sewerage, electrical) the promoter declared complete when this project was registered with HRERA — a snapshot at registration, and infrastructure, not building / tower construction. Not a live tracker.Find your flat
Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.
Builder’s track record
HRERA Gurugram · Promoter registrationInfrastructures Pvt.
These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location
HRERA Gurugram · Registration filing- Address
- GOPALPUR, SECTOR 99A, GURUGRAM, HARYANA
- Tehsil
- HARSARU ST
- District
- GURUGRAM
Planning authority
HRERA Gurugram · Approved building planThe promised possession date (10 Oct 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — HRERA Gurugram does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — HRERA Gurugram does not publish a complaints register. This read cannot speak to them either way.