HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
1 units
Saleable area
629–1961 sq mper unit, as filed
Floors
12
Land area
4,180 sq m
Built-up area
17,565 sq m
Road widening
534 sq mland set aside for road widening

Timeline

RERA approvedFeb 2021
Proposed completionFeb 2027
TodayJul 2026
Construction progress

90% overall, as filed

Podiums0%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.
02

Builder’s track record

RERA Telangana · Promoter registration

DEFINATION SOFTWARE SOLUTIONS LLP

LLPPromoter type
Hyderabad, TelanganaBased in
1Projects
1City
2021–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Surya Farm House
Mandal
Gandipet
District
Ranga Reddy
Pincode
500089
North boundary
Open Land No 15
East boundary
Part of Land in Survey No 336
South boundary
Open Land No 17
West boundary
40-0 wide road
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.8 kmPrimary road 2.5 km · Terminal 1 Approach RdNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 2.4 km
distances only — not a flood assessment
Declared external development
Roads100%
Water supply100%
Sewerage (Chamber,…100%
Rainwater100%
Green Strip/TOT LO…100%
Street lighting100%
Sewage100%
Solid waste100%
Rainwater100%
Renewable energy100%
Fire safety100%
Electricity100%
Community Building…0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 337
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.