Complete project overview

RERA Chhattisgarh · Registration filing
Units
92 units
Unit mix
92 × 1BHK
Quarterly reports
5 on filequarterly progress reports filed with RERA

Timeline

RERA registeredJan 2025
Proposed completionDec 2029
TodayJul 2026
Construction progress

12% overall, as filed

Water Supply0%
Storm Water Drains0%
Landscaping And Tree Planting0%
Street Lighting0%
Open Parking0%
Water Conservation Rain Water Harvesting0%
Energy Maanagement0%
Boundary Wall0%
Sewerage2%
Internal Roads And Footpaths3%
From the promoter's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

92 units across 2 batches
TypeArea sq mCount
1BHK10463
1BHK5629

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Chhattisgarh · Promoter registration

CHHATTISGARH HOUSING BOARD DIVISION-KAWARDHA

Government/Semi Government AgencyPromoter type
6Projects
4Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,062 homeson the public record across 6 projects
₹161.07 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Chhattisgarh · Registration filing
District
Kabirdham
Tehsil
Kawardha
Address
Construction of 63 No LIG & 29 No. EWS Houses and Development Work of 2.493 Hectare Land under Schem
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.5 kmPrimary road 2.8 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 1.9 kmRiver 2.0 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹20.11 Cr declared to build 92 flats. What that works out to:

₹21.86 Lakhdeclared cost per flatall-in — land + construction
22%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

Complaints register

None on record with RERA Chhattisgarh against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.