Complete project overview

RERA Karnataka · Registration filing
Status
New Project Launch
Land area
44,087 sq m
Covered area
32,733 sq m
Open area
11,353 sq m

Timeline

Project startedOct 2021
RERA registeredOct 2021
Proposed completionOct 2026
TodayJul 2026
02

Builder’s track record

RERA Karnataka · Promoter registration

KARNATAKA SLUM DEVELOPMENT BOARD

Bengaluru UrbanBased in
200Projects
119Cities
2019–presentActive
Timelineevery project, start → promised completion
Construction of 759 DU's in Bangalore cityPMAY-HFA (U)Construction of 450 (G.F) Du's Including InfrastrConstruction of 450 (G.F) Du's Including InfrastrConstruction of 1588 DUs in SAGARA CityConstruction of 843 DU's at KGFCONSTRUCTION OF 860 GROUND FLOOR DWELLING UNITSConstruction of 230 Ground Floor Dwelling units iConstruction of 1530(GF) RamanagaraSARVAGNANAGAR762PMAY-HFAGANDHINAGAR933construction of 1329 Dus in mysorePMAY HFA (U)Construction of 829 (GF) Dus in Belagavi CityConstruction of 525 (G & G+3) DUs in Hubli city.construction of 400 houses @ Bhalki townPMAY-HFA(U)Construction of 655 GF DU's in Mysoreconstruction of 1500 houses in Bidar townConstruction of 700 G.F. D.U's in N.R.ConstituenyConstruction of 1188 (GF) in Ballari CityGovindarajanagara and Vijayanagara 1607 housesCONSTRUCTION OF 500 DUs IN MANGALORE CITYCONSTRUCTION OF 404 DUSConstruction of 801GF DUs in Harihara townCONSTRUCTION OF 250 GF DUs IN HANGAL TOWNCONSTRUCTION OF 250 GF DUs IN BYADAGI TOWNConstruction of 486(GF) DUs at ArakalugudConstruction of 500 DU'sConstruction of 1008 (G+2) Houses at Sira CityVIJAYANAGARA 1378 HOUSESConstruction of 1300(G+2) DUs in Hubli cityJAYANAGARA CHAMARAJAPETE CHIKKAPETE 931CONSTRUCTIN OF 210 DUS (GF) IN RONA TOWNPMAY HFA (U)CONSTRUCTION OF 500 (GF) DU's HOUSESConstruction of 213GF DUs at Haliyal town.PMAY HFA (U)Construction of 250 (GF) DUs under PMAY HFA (U)Construction of 250 (GF) DUs at Rabkavi BanhattiKamalapura 491 Du'sCONSTRUCTION OF 250 (GF) DU'S HOUSESConstruction of 250 housesBallari 1613 Du'sConstruction of 500 (G.F) Du's Including InfrastrConstruction of 500 GF Du's in SiddlaghattaConstruction of 242GF Du's in ChikkaballapuraPMAY-HFA (U)CONSTRUCTION OF 250 (GF) DUS UNDER PMAY HFA (U)Construction of 250 (GF) DUs Under PMAY HFA (U)Construction of 287GF dwelling units at DandeliPMAY HFA (U)PMAY-HFA (U)Construction of 250 houses at yadgiri city.PMAY-HFA (U)PMAY-HFA(U)Construction of 600 Houses at SrinivasapuraTekkalakote 268 Du'sPMAY-HFA( U)Construction of 200 (G.F) Du's Including Infrastrconstruction of 457 houses at T Dasarahalliconstruction of 893 GF DU's in Bangalore cityConstruction of 250 DU's in Soraba town.PMAY-HFA (U)CONSTRUCTIONS OF 300 DU'S IN PAVAGADA TOWNPMAY-HFA (U)construction of 250 (GF) houses at Maddur TownConstruction of 250(GF) Du's in nagamangala TownConstruction of 250 DU's in Shiralakoppa town.Construction of 500(GF) UNITSPMAY-HFAConstruction of 301(GF)DUs in Kudchi TownCONSTRUCTION OF 500 DU'S IN UDUPI CITYPMAY-HFA (U)Construction of 500 DU's at Mulabagiluconstruction of 250 (GF) DU's houses 01 slumPMAY HFA (U)Construction of 500 DUs in Kalghatagi town.construction of 250 (GF) housesConstruction of 500 D.U.'s in Hunsur TownCONSTRUCTION OF 250 (GF) HOUSESconstruction of 400 houses @ JewargiConstruction of 1800 (GF) DUs in Vijayapura cityConstruction of 1590 DU's in Shivamogga city.Construction of 500 (GF) DU's in kollegala townConstruction of 500 (GF) DUs in Bilagi townPMAY-HFAPMAY-HFAConstruction of 250 (GF) Dusconstruction of 500(GF) housesCONSTRUCTION OF 1000 (GF+1) DU'sConstruction of 449 (GF) DUs at Chikkodi TownCONSTRUCTION OF 300 (GF) DU'S IN BANNUR TOWNconstruction of 400 houses @ sedam townConstruction of 768 G+3 Houses at KR PuramPMAY HFA (U)Construction of 346 DU's ByatrayanpuraConstruction of 500 (GF)Dus in Chamarajnagar townChikkapete500chikkapetechamrajpete1155Construction of 200(GF) DUs in T narasipura TownConstruction of 500 (GF) DUs at ChannarayapatnaConstruction of 460 (GF)DUs in holenarasipuraCONSTRUCTION OF 280DU'SCONSTRUCTION OF 250 DU'SConstruction of 250(GF) Units at SakleshpuraConstruction of 327 (GF) Units including infrastGovindarajanagara 1845 housesSARVAGNANAGAR616Shanthinagar350BANGALORE SOUTH AND BASAVANAGUDI 1699construction of 825 G.F.DU's in N.R.ConstituencySHIVAJINAGAR 500 DUS BANGALOREGANDHINAGAR500CONSTRUCTION OF 500 DU S IN BHADRAVATHI CITYconstruction of 588 multi storied G+3 unitsCONSTRUCTION OF 300 (GF) DU'S IN NANJANGUDUConstruction of 485 DU'sConstruction of 300 DU's at ByatarayanpuraCONSTRUCTION OF 516(GF) INDIVIDUAL UNITSCONSTUCTION OF 1002 DUS IN CHANNAGIRI TOWNConstruction of 888 (G+3) Dus atRamanagaraConstruction of 625 Houses @ HubliDharwad centralConstruction of 200 houses in Nelamangla TownConstruction of 250 dus at sindhanuru townConstrution of 500 Houses in BasvangudiConstruction of 423 Houses in Vijayappura & DevanConstruction of 1450 Houses in Tumkur CityConstruction of 1200 (GF) HOUSES at BommanahalliConstruction of 1350 @ Hubli-Dharwad cityConstruction of 1200 houses in Tiptur CityConstruction of 1176 Houses at Dandeli townConstruction of 760 Dus in chikkaballapura TownConstruction of 300 houses in gubbi TownConstruction of 1430 Houses in CV Raman NagarDavangere_895@PMAY-HFAConstruction of 588 Houses at Nippani TownJAGALURU_300@PMAY-HFAChitradurga City -1226 dus under PMAY(U)-HFA.Chitradurga City-292 DUS under PMAY(U)-HFAHolalkere Town - 206 dus under PMAY(U)-HFA.Construction of 800 House in chikkanayakanahalliConstruction of 520 houses in Koratagere TownConstruction of 612 houses in Shidlaghatta TownDavangere North - 828 DUS under PMAY(U)-HFAConstruction of 500 Houses at NaragundConstruction of 798 @ AthaniConstruction of 235 Houses at Kundagola TownKOTTURU_411@PMAY-HFAConstruction of 250 Houses at Kalaghatagiconstruction 375 Dus at Navalgunda Town.Construction of 906 Houses at Mundagod townConstruction of 411 Houses at Kumta Town.Construction of 905 Houses at Belagavi NorthConstruction of 200 Houses at karwarConstruction of 469 @ KhanapuraConstruction of 300 Houses at Rona/GajendragadConstruction of 661 houses at Haliyal TownConstruction of 313 @ BhtkalaMolakalmuru Town_500 dus under PMAY-HFAConstruction of 863 Houses at Gadag CityConstruction of 1748 @ Belagavi SouthConstruction of 873 at Kuduchi Town.Construction of 643 Houses at Yelaburga townConstruction of 705 Houses at Bailhongal Town.Construction of 1035 @ RaybagConstruction of 275 Houses at Badami TownConstruction of 983 houses at Savadatti TownConstruction of 565 Houses at Rabakavi BanahattiConstruction of 400 @ SavadattiConstruction of 250 Houses at Teradal Town.Construction of 750 Dus at Davadurga TownKARNATAKA SLUM DEVELOMENT BOARDCONSTUCTION OF 1473 DUS IN SHAHABAD CITYCONSTRUCTION OF 552 g+2 DUS IN BASAVAKALYANA TOWNCONSTRUCTION OF 800 DUS IN BASAVAKALYANA TOWNHIRIYUR @ 988 DUS UNDER PMAY-HFAHonnali Town - 351 DUS under PMAY(U)-HFA.HOSADURGA 700 DUS under PMAY(U)-HFA.PMAY-HFA(U)Kamalapura_446 Dus under PMAY-HFA(U)Harapanahalli Town - 1156 DUS under PMAY(U)-HFAKampli Town - 500 DUS under PMAY(U)-HFA.Siruguppa Town - 598 DUS under PMAY(U)-HFAHuvinahadgali Town - 741 DUS under PMAY(U)-HFAConstruction of 455 Houses including infrastructuPMAY HFA (U)PMAY(HFA) RANEBENNUR 887PMAY 1500 MahalakshmipuramPMAY-HFA 500 GOVINDARAJANAGARAPMAY HFAPMAY_HFA@JEWARGI-750PMAY-HFA@Bidar-750PMAY HFAPMAY-HFA@BALLARI_609PMAY-HFA @BANKAPURA 454DUSPMAY-HFA @ HANAGAL 1000DUSPMAY 976 DHARWADPMAY HFA
Builder DNAthe whole portfolio, summed
1,002 homeson the public record across 200 projects
56,49,392 sq mland declared
₹7199.89 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
KSDB - Karnataka State Slum Development Boardthis project189 of 200 projects
Local Planning AuthorityTown & Country Planning (DTCP)10 of 200 projects
BBMP - Bruhat Bengaluru Mahanagara PalikeMunicipal / Corporation1 of 200 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Belagavi
District
Dharwad
Pincode
580004
Address
Harijankeri , Near Killa , Savalbhavi, Gaurikeri, Sy No. 9/A/1A/1/1/A
What’s nearby
Schools1 school within 500m · 8 educational institutions within 1km · College or university 397m away
HealthcareHospital 649m away · 3 clinics within 1km
LifestyleNo parks within 2km · 5 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Bank 501m away · ATM within 500m
Getting around
Primary road 328 m · Pune Bangalore RoadRailway line 1.2 kmRailway station 1.7km away (Dharwad)Limited bus connectivity nearby
Water & environment
Water body 567 m · Hirekere
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹66.44 Cr declared. What that works out to:

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

KSDB - Karnataka State Slum Development Board

Building Permit
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

KSDB

Planning authority · Karnataka State Slum Development Board

Has approved 282 RERA projects3.2% of Karnataka.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
31
On record
1,002 flats · 0 plots
Reach
141 taluks
Since
2019

More apartment-heavy than Karnataka overall — 100% apartments here vs 62% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.