Complete project overview

RERA Karnataka · Registration filing
Status
Ongoing
Land area
24,281 sq m
Covered area
555 sq m
Open area
23,726 sq m

Timeline

RERA registeredDec 2020
Project startedFeb 2021
Proposed completionNov 2021
TodayJul 2026
02

Builder’s track record

RERA Karnataka · Promoter registration

MUNICIPLE COMMISSIONER

ChikkaballapuraBased in
1Projects
1City
2020–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Gauribidanur
District
Bengaluru Urban
Pincode
560020
Address
Madanahalli Village S.no.11,12,13, 217, 283,287 and 317 Kasaba Hobli, Gouribidanur Taluk
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 210 mRailway line 822 mRailway station 2.3km away (Gollahalli)Bus stop within 500m
Water & environment
Water body 1.4 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹1.10 Cr declared. What that works out to:

109%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

Chikkaballapur Urban Development Authority

Urban Development Authority
Building Permit

The promised possession date (21 Nov 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Chikkaballapur Urban Development Authority

Urban Development Authority

Has approved 105 RERA projects1.2% of Karnataka.

a plotted-layout market8% apartments · 92% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
89
On record
69 flats · 4,347 plots
Reach
12 taluks
Since
2017

More layout-heavy than Karnataka overall — 92% plots here vs 38% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — RERA Karnataka does not publish a complaints register. This read cannot speak to them either way.