Complete project overview

WBRERA · Registration filing
Apartments
20
Land area
405 sq m
Built-up area
1,030 sq m
Carpet area
863 sq m
Parking
42 spaces
RERA registered
2026

Timeline

RERA registeredJan 2026
Proposed completionMay 2027
TodayJul 2026
02

Builder’s track record

WBRERA · Promoter registration

Nirman Consultant

Proprietorship FirmPromoter type
East Medinipur, West BengalBased in
2Projects
1City
2025–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
36 homeson the public record across 2 projects
2,132 sq mbuilt-up filed
770 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

WBRERA · Registration filing
District
East Medinipur
Municipality / area
Tamluk Municipality
Police station
Tamluk
Address
Salgechia Ward No - 17
Pincode
721636
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 94m away · 4 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.3 kmPrimary road 26 m · Tamluk-Mecheda RoadRailway line 390 mRailway station 679m away (Tamluk)Bus stop within 1km
Water & environment
Water body 689 m · Hut PukurCanal 818 mRiver 2.9 km · Rupnarayan
distances only — not a flood assessment
04

Planning authority

WBRERA · Approved building plan

Tamralipta Municipality

Municipality
Building Permit no. SWS-OBPAS/1705/2024/0155
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan SWS-OBPAS/1705/2024/0155 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Tamralipta Municipality

Municipal corporation / municipality

Has approved 8 RERA projects0.3% of West Bengal.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
8
On record
142 flats · 0 plots

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Compliance & litigation record
Defaulter listThis developer appears on WBRERA's defaulter list
LitigationLitigation declared by the promoter at registration
WBRERA lists the developers it has flagged as defaulters — that line is the authority's own record; any litigation line is the promoter's own declaration at registration. A flagged line is worth verifying directly with WBRERA; none of it is a verdict on the project.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — WBRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — WBRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — WBRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.