Complete project overview

RERA Telangana · Registration filing
Units
15 units
Unit mix
10 × 3BHK, 5 × 2BHK
Saleable area
111–176 sq mper unit, as filed
Floors
5
Land area
732 sq m
Built-up area
1,822 sq m

Timeline

RERA approvedJan 2022
Proposed completionJan 2025
TodayJul 2026
Construction progress

90% overall, as filed

Podiums0%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

5 of 15 available
BuildingFloorTypeArea sq mAvailable
DEVARAKONDA DIVINE13BHK1761 of 1
DEVARAKONDA DIVINE13BHK1660 of 1
DEVARAKONDA DIVINE12BHK1110 of 1
DEVARAKONDA DIVINE23BHKmortgaged1761 of 1
DEVARAKONDA DIVINE23BHK1660 of 1
DEVARAKONDA DIVINE22BHKmortgaged1110 of 1
DEVARAKONDA DIVINE33BHK1761 of 1
DEVARAKONDA DIVINE33BHK1660 of 1
DEVARAKONDA DIVINE32BHK1110 of 1
DEVARAKONDA DIVINE43BHK1761 of 1
DEVARAKONDA DIVINE43BHK1660 of 1
DEVARAKONDA DIVINE42BHK1110 of 1
DEVARAKONDA DIVINE53BHK1761 of 1
DEVARAKONDA DIVINE53BHK1660 of 1
DEVARAKONDA DIVINE52BHK1110 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

DEVARAKONDA BUILDERS AND DEVELOPERS

PartnershipPromoter type
Medchal-Malkajgiri, TelanganaBased in
8Projects
3Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
117 homeson the public record across 8 projects
11,786 sq mbuilt-up filed
4,749 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Kapra
Village
Kapra
Mandal
Kapra
District
Medchal-Malkajgiri
Pincode
500062
North boundary
Plot Nos 74 and 75
East boundary
Plot Nos 60 and 17
South boundary
Plot No 1
West boundary
30 Feet Wide Road
What’s nearby
SchoolsNearest school 1.1km away
HealthcareHospital 35m away · Clinic within 2km
LifestyleNo parks within 2km · Gym or sports centre 985m away · 34+ restaurants and cafes within 1km
ShoppingSupermarket 403m away · Mall 266m away · Bank 287m away
Getting around
Primary road 63 m · Kushaiguda RoadRailway line 2.6 kmRailway station 3.8km away (Neredmet)Bus stop within 500m
Water & environment
Water body 214 m
distances only — not a flood assessment
Declared external development
Roads100%
Water supply100%
Sewerage (Chamber,…100%
Green Strip/TOT LO…100%
Sewage100%
Rainwater100%
Electricity100%
Rainwater0%
Street lighting0%
Community Building…0%
Solid waste0%
Renewable energy0%
Fire safety0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 612 TO 618 AND 619

The promised possession date (6 Jan 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.