HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
10 × 3BHK
Saleable area
211–242 sq mper unit, as filed
Floors
5
Land area
831 sq m
Built-up area
1,961 sq m
Road widening
87 sq mland set aside for road widening

Timeline

RERA approvedAug 2019
Proposed completionDec 2021
TodayJul 2026
Construction progress

83.5% overall, as filed

Podiums0%
External finishes70%
OC-readiness80%
Flat fit-out90%
Internal finishes95%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Stairs & lifts100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

9 of 10 available
BuildingFloorTypeArea sq mAvailable
DREAM HOMES SUMERU13BHKmortgaged2421 of 1
DREAM HOMES SUMERU13BHKmortgaged2111 of 1
DREAM HOMES SUMERU23BHK2421 of 1
DREAM HOMES SUMERU23BHK2111 of 1
DREAM HOMES SUMERU33BHK2421 of 1
DREAM HOMES SUMERU33BHK2111 of 1
DREAM HOMES SUMERU43BHK2421 of 1
DREAM HOMES SUMERU43BHK2111 of 1
DREAM HOMES SUMERU53BHK2420 of 1
DREAM HOMES SUMERU53BHK2111 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

DREAM HOME BUILDERS AND DEVELOPERS

PartnershipPromoter type
Hyderabad, TelanganaBased in
1Projects
1City
2019–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
YELLAREDDY GUDA 10A
Village
YELLAREDDYGUDA
Mandal
KHAIRTABAD
District
Hyderabad
Pincode
500073
North boundary
PLOT OF PINGALA VENKATA RAMA REDDY
East boundary
PLOT NO 103
South boundary
60 FEET WIDE MAIN ROAD BEFORE ROAD WIDENING 40 FT
West boundary
PLOT NO 101
What’s nearby
Schools2 schools within 500m · 12 educational institutions within 1km · College or university 626m away
HealthcareHospital 332m away · 10 clinics within 1km · Pharmacy within 500m
Lifestyle2 parks within 500m · Gym or sports centre 1.1km away · 35+ restaurants and cafes within 1km
ShoppingSupermarket 374m away · Mall 573m away · Bank 77m away
Getting around
Expressway 515 m · Ameerpet Road - Panjagutta Main RoadPrimary road 326 m · Road No. 3Railway line 1.7 kmMetro station 602m away (Ameerpet (Blue Line))3 bus stops within 500m
Water & environment
Water body 366 m
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 1/C17/12234/2019Survey no. 8 BLOCK 3

The promised possession date (31 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1/C17/12234/2019 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.