HORIZONMarkets
01

Complete project overview

UP-RERA · Registration filing
Units
114 units
Unit mix
90 × 2 BHK · 9 × OTHER · 9 × 1 BHK · 6 × SHOP
Carpet area
4–64 sq mper unit, as filed
Floors
12
Blocks
3
Land area
5,768 sq m

Timeline

RERA registeredMay 2018
Project startedJul 2018
Proposed completionMay 2023
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

114 units across 54 batches
BuildingFloorTypeArea sq mCount
EWSGFOTHER224
EWSGFOTHER231
EWS1OTHER223
EWS1OTHER231
LIGGF1 BHK314
LIG11 BHK314
LIG21 BHK311
samridhhiGFSHOP202
samridhhiGFSHOP44
samridhhi12 BHK612
samridhhi12 BHK602
samridhhi12 BHK642
samridhhi12 BHK632
samridhhi22 BHK612
samridhhi22 BHK602
samridhhi22 BHK642
samridhhi22 BHK632
samridhhi32 BHK612
samridhhi32 BHK602
samridhhi32 BHK642
samridhhi32 BHK632
samridhhi42 BHK612
samridhhi42 BHK602
samridhhi42 BHK642
samridhhi42 BHK632
samridhhi52 BHK612
samridhhi52 BHK602
samridhhi52 BHK642
samridhhi52 BHK632
samridhhi62 BHK612
samridhhi62 BHK602
samridhhi62 BHK642
samridhhi62 BHK632
samridhhi72 BHK612
samridhhi72 BHK602
samridhhi72 BHK642
samridhhi72 BHK632
samridhhi82 BHK602
samridhhi82 BHK612
samridhhi82 BHK642
samridhhi82 BHK632
samridhhi92 BHK602
samridhhi92 BHK612
samridhhi92 BHK642
samridhhi92 BHK632
samridhhi102 BHK602
samridhhi102 BHK612
samridhhi102 BHK642
samridhhi102 BHK632
samridhhi112 BHK602
samridhhi112 BHK612
samridhhi112 BHK642
samridhhi112 BHK632
samridhhi122 BHK642

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

DREAMZ INFRAREALTY PRIVATE LIMITED

CompanyPromoter type
1Registered projects
1Projects
1City
2018–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Lucknow
Tehsil
Sarojini Nagar
Site access
on Bijnaur Sisendi Highway
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.8 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Canal 305 mWater body 1.2 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹14.54 Cr declared to build 114 flats. What that works out to:

₹12.75 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 23 Mar 2018 · 8 yrs ago
Building Permit no. 764

The promised possession date (1 May 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 764 on the approving authority’s portal to confirm the sanction.

Complaints register

None on record with UP-RERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.