Complete project overview

RERA Assam · Registration filing
Registration category
NEWnew vs ongoing at registration
Apartments / villas
334 units
Land area
1,003 sq m
Local land measure
3 Kathas 15 Lechas
RERA validity
4 Sep 2026
Completion
Occupancy / Completion Certificate on record

Timeline

Proposed completionJul 2023
RERA registeredSep 2024
TodayJul 2026
02

Builder’s track record

RERA Assam · Promoter registration

BUILD TECH (PROPRIETOR MONIDEEPA BORPUJARI)

Firm/ Proprietorship FirmPromoter type
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Assam · Registration filing
District
KAMRUP METRO
Mouza / circle
DISPUR
Town / village
Guwahati, Vill- Dharandha
Landmark
Near Namghar
Site address
NAMGHAR PATH, JURIPAR, PANJABARI ROAD
Pincode
781022
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.9km away · 1 clinic within 1km
LifestylePark 769m away
ShoppingNo supermarket within 2km
Getting around
Expressway 1.9 km · Khanapara FlyoverPrimary road 1.8 kmRailway line 1.7 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 806 mRiver 1.4 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹5.36 Cr declared to build 334 flats. What that works out to:

₹1.61 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Assam · Approved building plan

Guwahati Municipal Corporation

Municipal Corporation
Building Permitapproved 3 Sep 2019 · 6 yrs ago

The promised possession date (31 Jul 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Occupancy Certificate — the occupancy sign-off, on record

An Occupancy / Completion Certificateis on this project’s RERA Assam record — the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit and block before you rely on it.

The approving body, at scale

Guwahati Municipal Corporation

Municipal corporation / board

Has approved 604 RERA projectsabout 1 in 1 in Assam, more than any other body in the state.

an apartments market98% apartments · 2% plotted layouts. Apartments like yours are this body's core business.

Builders
488
On record
45,695 flats · 10,758 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Assam does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Assam does not publish a complaints register. This read cannot speak to them either way.