Complete project overview

RAJ-RERA · Registration filing
Units
369 units
Mix
241 × LIG 2 BHK · 117 × EWS 1 BHK · 10 × Commercial Shop No. 1 to 2 & 4 to 11 · 1 × Commercial Shop No. 3
Carpet area
15–41 sq mper-type range, as filed
Land area
5,361 sq m
Completion deadline extended
3 extensions on record — latest to 4 Dec 2026declared reason: force majeure
Description
1. The finish date committed for the project as per Form "B" is 04/12/2022.Which is beyond the validity period of the approved maps. The promoter takes the responsibility to obtain the necessary extension from the competent authority. 2. As per approved Maps Total EWS units = 117 and LIG units = 241 and commercial units = 11. 3. Total Apartments of the project =411 out of which 369 apartments are sanctioned and 42 are proposed but not sanctioned. 4. Sanctioned Apartments= 369 which includes EWS units = 117 and LIG units = 241 and commercial units = 11. 5. Not Sanctioned Apartments=42 which includes 13 EWS apartment and 27 LIG apartment of 10th floor (However the sanctioned for 10th floor plan has not been issued by UIT Kota, However the 10th floor has been depicted crossed in the sanctioned sheet on Elevation and Section sheet) and 2 apartment of 9th floor has also been depicted cross on the sanctioned sheet. 6. Gross area of project= 6740 sq. mtr. which includes surrender Road area=1042 sq mtr and surrender facility area=337 sq. mtr. ,Net area after surrender of the project=5361 sq. mtr. (As depicted on sanctioned layout sheet however the other table depicting the area calculation been crossed by UIT Kota and is to be ignored) 7. Approval letter of the project approved from UIT kota is on the name of the firm "M/s FAZAL ASSOCIATES" with other partners name as Mohammad Sarfraj, Ashish Soni, Purshuttam Soni, Omprakash Yadav. There is not mentioned name of the one partner Vijay Sharma. (Which is typo error and to be ignored) 8. As per condition no. 5 of the building plan approval letter dated 05/12/2018 issued by UIT Kota vide letter no. एफ 7/डी०टी०पी०/2018/312-24 permission for height above 30 mtr and BAR more than 3.375 shall be released in second stage after the approval of state government. We have applied for the end date of the project by considering the total project including the conditionally sanctioned units (i.e. above 30 mtr height more than 3.375 BAR).

Timeline

Construction startDec 2018
RERA registeredMar 2019
Proposed completionDec 2022
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

369 units across 9 batches
BuildingTypeArea sq mCount
EKTA RESIDENCYLIG 2 BHK4163
EKTA RESIDENCYLIG 2 BHK2836
EKTA RESIDENCYLIG 2 BHK4134
EKTA RESIDENCYLIG 2 BHK4154
EKTA RESIDENCYEWS 1 BHK28108
EKTA RESIDENCYLIG 2 BHK4154
EKTA RESIDENCYEWS 1 BHK289
EKTA RESIDENCYCommercial Shop No. 1 to 2 & 4 to 111510
EKTA RESIDENCYCommercial Shop No. 3201

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

FAZAL ASSOCIATES

OrganisationPromoter type
Kota, RajasthanBased in
1Projects
1City
2019–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
274/144, 275/144 (PART), 279/145 (PART), 145 (PART), MANPURA, MANPURA, Ladpura, Kota, 324002
Village
MANPURA
Taluka
Ladpura
District
Kota
Pincode
324002
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 925m away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.2 km · Kota BypassPrimary road 4.2 kmRailway line 1.6 km · Mumbai - Delhi RailwayRailway station 4.2km away (Kota Junction)Limited bus connectivity nearby
Water & environment
Canal 1.3 kmWater body 2.1 kmRiver 2.7 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹39.60 Cr declared to build 369 flats. What that works out to:

₹10.73 Lakhdeclared cost per flatall-in — land + construction
₹1,651/sq ftof built-up area₹17,775/sq m
15%of the cost is land₹996/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 8 Mar 2019 · 7 yrs ago

The promised possession date (4 Dec 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.