HORIZONMarkets
01

Complete project overview

RERA Madhya Pradesh · Registration filing
Units
3 flats

Timeline

Project startedMar 2026
RERA registeredJun 2026
Proposed completionMar 2028
TodayJul 2026
02

Builder’s track record

RERA Madhya Pradesh · Promoter registration

BUILDWELL VENTURES

Partnership Firm / LLPPromoter type
1Projects
1City
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Madhya Pradesh · Registration filing
District
Indore
Tehsil
Sawer
Planning area
Other
Address
Plot no. D-05, Shankheshwar city, Village-Jakhiya Tehsil- Sanwer District- Indore (M.P.)
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 276m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 1.3 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 492 m · Kanh RiverWater body 1.9 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹2.81 Cr declared to build 3 flats. What that works out to:

₹93.74 Lakhdeclared cost per flatall-in — land + construction
29%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Madhya Pradesh · Approved building plan
Building Permitapproved 3 Jun 2026 · 1 mo ago
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — RERA Madhya Pradesh does not publish a complaints register. This read cannot speak to them either way.