Complete project overview

RERA Telangana · Registration filing
Units
115 units
Unit mix
60 × 3BHK, 55 × 2BHK
Saleable area
103–146 sq mper unit, as filed
Floors
5
Buildings
2
Land area
6,613 sq m
Built-up area
14,213 sq m
Road widening
113 sq mland set aside for road widening

Timeline

RERA approvedMay 2019
Proposed completionMay 2025
TodayJul 2026
Construction progress

0.5% overall, as filed

Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Excavation5%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

115 of 115 available
BuildingFloorTypeArea sq mAvailable
BUILDING - A13BHK1383 of 3
BUILDING - A13BHK1401 of 1
BUILDING - A12BHK1061 of 1
BUILDING - A13BHKmortgaged1421 of 1
BUILDING - A12BHKmortgaged1062 of 2
BUILDING - A13BHKmortgaged1383 of 3
BUILDING - A12BHKmortgaged1041 of 1
BUILDING - A13BHK1031 of 1
BUILDING - A23BHK1386 of 6
BUILDING - A23BHK1401 of 1
BUILDING - A22BHK1063 of 3
BUILDING - A23BHK1421 of 1
BUILDING - A22BHK1041 of 1
BUILDING - A23BHK1031 of 1
BUILDING - A33BHK1386 of 6
BUILDING - A33BHK1401 of 1
BUILDING - A32BHK1063 of 3
BUILDING - A33BHK1421 of 1
BUILDING - A32BHK1041 of 1
BUILDING - A33BHK1031 of 1
BUILDING - A43BHK1386 of 6
BUILDING - A43BHK1401 of 1
BUILDING - A42BHK1063 of 3
BUILDING - A43BHK1421 of 1
BUILDING - A42BHK1041 of 1
BUILDING - A43BHK1031 of 1
BUILDING - A53BHK1386 of 6
BUILDING - A53BHK1401 of 1
BUILDING - A52BHK1063 of 3
BUILDING - A53BHK1421 of 1
BUILDING - A52BHK1041 of 1
BUILDING - A53BHK1031 of 1
BUILDING - B13BHKmortgaged1382 of 2
BUILDING - B12BHKmortgaged1171 of 1
BUILDING - B12BHKmortgaged1041 of 1
BUILDING - B12BHK1181 of 1
BUILDING - B13BHK1461 of 1
BUILDING - B12BHKmortgaged1232 of 2
BUILDING - B12BHKmortgaged1062 of 2
BUILDING - B23BHK1461 of 1
BUILDING - B22BHK1232 of 2
BUILDING - B23BHK1382 of 2
BUILDING - B22BHK1062 of 2
BUILDING - B22BHK1171 of 1
BUILDING - B22BHK1041 of 1
BUILDING - B22BHK1181 of 1
BUILDING - B33BHK1461 of 1
BUILDING - B32BHK1232 of 2
BUILDING - B33BHK1382 of 2
BUILDING - B32BHK1062 of 2
BUILDING - B32BHK1171 of 1
BUILDING - B32BHK1041 of 1
BUILDING - B32BHK1181 of 1
BUILDING - B43BHK1461 of 1
BUILDING - B42BHK1232 of 2
BUILDING - B43BHK1382 of 2
BUILDING - B42BHK1062 of 2
BUILDING - B42BHK1171 of 1
BUILDING - B42BHK1041 of 1
BUILDING - B42BHK1181 of 1
BUILDING - B53BHK1461 of 1
BUILDING - B52BHK1232 of 2
BUILDING - B53BHK1382 of 2
BUILDING - B52BHK1062 of 2
BUILDING - B52BHK1171 of 1
BUILDING - B52BHK1041 of 1
BUILDING - B52BHK1181 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

ESSEN INFRA GROUP

PartnershipPromoter type
Hyderabad, TelanganaBased in
1Projects
1City
2019–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
JEEDIMRTLA
Mandal
Qutballapur
District
Medchal-Malkajgiri
Pincode
500055
North boundary
VILLAGE ROAD
East boundary
NALA
South boundary
BEERAPPAS LAND
West boundary
B MADHAVARAO AND OTHERS LAND
What’s nearby
SchoolsNearest school 1.6km away · College or university 1.5km away
HealthcareHospital 1.2km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingSupermarket 861m away · Mall 1.3km away
Getting around
Expressway 2.3 km · Nizamabad RoadPrimary road 1.3 km · Jeedimetla Main RoadRailway line 3.0 kmRailway station 3.7km away (Suchitra Centre)Limited bus connectivity nearby
Water & environment
Canal 794 mWater body 1.3 km · Fox Sagar
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 1/C25/07733/2019Survey no. 108

The promised possession date (7 May 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1/C25/07733/2019 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.