HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
224 units
Unit mix
131 × 2BHK, 89 × 3BHK, 4 × Banquet Hall
Saleable area
99–162 sq mper unit, as filed
Floors
5
Buildings
5
Land area
10,354 sq m
Built-up area
28,401 sq m

Timeline

RERA approvedJan 2023
Proposed completionJan 2026
TodayJul 2026
Construction progress

35% overall, as filed

Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal finishes10%
Stilt floor25%
Flat fit-out25%
Superstructure30%
Podiums60%
Excavation100%
Basement & plinth100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

224 of 224 available
BuildingFloorTypeArea sq mAvailable
BLOCK A12BHKmortgaged997 of 7
BLOCK A13BHKmortgaged1326 of 6
BLOCK A13BHKmortgaged1281 of 1
BLOCK A23BHK1326 of 6
BLOCK A22BHK997 of 7
BLOCK A23BHK1281 of 1
BLOCK A33BHK1326 of 6
BLOCK A32BHK997 of 7
BLOCK A33BHK1281 of 1
BLOCK A43BHK1326 of 6
BLOCK A42BHK997 of 7
BLOCK A43BHK1281 of 1
BLOCK A53BHK1326 of 6
BLOCK A52BHK997 of 7
BLOCK A53BHK1281 of 1
BLOCK B13BHKmortgaged1323 of 3
BLOCK B12BHKmortgaged996 of 6
BLOCK B13BHKmortgaged1271 of 1
BLOCK B22BHK996 of 6
BLOCK B23BHK1271 of 1
BLOCK B23BHK1323 of 3
BLOCK B33BHK1323 of 3
BLOCK B32BHK996 of 6
BLOCK B33BHK1271 of 1
BLOCK B43BHK1323 of 3
BLOCK B42BHK996 of 6
BLOCK B43BHK1271 of 1
BLOCK B53BHK1323 of 3
BLOCK B52BHK996 of 6
BLOCK B53BHK1271 of 1
BLOCK C12BHKmortgaged997 of 7
BLOCK C13BHKmortgaged1271 of 1
BLOCK C13BHKmortgaged1322 of 2
BLOCK C22BHK997 of 7
BLOCK C23BHK1271 of 1
BLOCK C23BHK1322 of 2
BLOCK C33BHK994 of 4
BLOCK C33BHK1271 of 1
BLOCK C33BHK1271 of 1
BLOCK C32BHK993 of 3
BLOCK C33BHK1321 of 1
BLOCK C42BHK997 of 7
BLOCK C43BHK1271 of 1
BLOCK C43BHK1322 of 2
BLOCK C52BHK997 of 7
BLOCK C53BHK1271 of 1
BLOCK C53BHK1322 of 2
BLOCK D13BHKmortgaged1322 of 2
BLOCK D12BHKmortgaged1021 of 1
BLOCK D12BHKmortgaged991 of 1
BLOCK D12BHKmortgaged1071 of 1
BLOCK D13BHKmortgaged1401 of 1
BLOCK D12BHKmortgaged994 of 4
BLOCK D23BHK1322 of 2
BLOCK D22BHK1021 of 1
BLOCK D22BHK991 of 1
BLOCK D22BHK1071 of 1
BLOCK D23BHK1401 of 1
BLOCK D22BHK994 of 4
BLOCK D33BHK1322 of 2
BLOCK D32BHK1021 of 1
BLOCK D32BHK991 of 1
BLOCK D32BHK1071 of 1
BLOCK D33BHK1401 of 1
BLOCK D32BHK994 of 4
BLOCK D43BHK1322 of 2
BLOCK D42BHK1021 of 1
BLOCK D42BHK991 of 1
BLOCK D42BHK1071 of 1
BLOCK D43BHK1401 of 1
BLOCK D42BHK994 of 4
BLOCK D53BHK1322 of 2
BLOCK D52BHK1021 of 1
BLOCK D52BHK991 of 1
BLOCK D52BHK1071 of 1
BLOCK D53BHK1401 of 1
BLOCK D52BHK994 of 4
CLUB HOUSE1Banquet Hall1621 of 1
CLUB HOUSE2Banquet Hall1621 of 1
CLUB HOUSE3Banquet Hall1621 of 1
CLUB HOUSE4Banquet Hall1621 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

GAHAN DEVELOPERS

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
1Projects
1City
2023–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
MEDCHAL
Village
Gundlapochampally
Mandal
Medchal
District
Medchal-Malkajgiri
Pincode
500089
North boundary
OTHERS LAND
East boundary
OTHERS LAND
South boundary
OTHERS LAND
West boundary
OTHERS LAND
What’s nearby
Schools1 school within 1km
HealthcareNearest hospital 2.8km away · Doctor's clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 327m away
Getting around
Expressway 1.7 kmPrimary road 2.4 km · Medak RoadRailway line 1.1 kmRailway station 1.2km away (Gundla Pochampally)Bus stop within 500m
Water & environment
Water body 607 m
distances only — not a flood assessment
Declared external development
Sewage10%
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 8/1,8/2,9,12,13 OF KAZIGUDA VILLAGE AND 8,8/A OF DOOLAPALLY VILLAGE

The promised possession date (21 Jan 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.