Complete project overview

UP-RERA · Registration filing
Units
209 units
Unit mix
204 × 2 BHK · 5 × 4 BHK
Carpet area
52–142 sq mper unit, as filed
Floors
18
Land area
5,118 sq m

Timeline

Project startedJun 2017
RERA registeredSep 2017
Proposed completionMay 2021
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

209 units across 53 batches
BuildingFloorTypeArea sq mCount
TOWER C12 BHK525
TOWER C12 BHK565
TOWER C12 BHK652
TOWER C22 BHK525
TOWER C22 BHK565
TOWER C22 BHK652
TOWER C32 BHK525
TOWER C32 BHK565
TOWER C32 BHK652
TOWER C42 BHK525
TOWER C42 BHK565
TOWER C42 BHK652
TOWER C52 BHK525
TOWER C52 BHK565
TOWER C52 BHK652
TOWER C62 BHK525
TOWER C62 BHK565
TOWER C62 BHK652
TOWER C72 BHK525
TOWER C72 BHK565
TOWER C72 BHK652
TOWER C82 BHK525
TOWER C82 BHK565
TOWER C82 BHK652
TOWER C92 BHK525
TOWER C92 BHK565
TOWER C92 BHK652
TOWER C102 BHK525
TOWER C102 BHK565
TOWER C102 BHK652
TOWER C112 BHK525
TOWER C112 BHK565
TOWER C112 BHK662
TOWER C122 BHK525
TOWER C122 BHK565
TOWER C122 BHK652
TOWER C132 BHK525
TOWER C132 BHK565
TOWER C142 BHK525
TOWER C142 BHK565
TOWER C144 BHK1421
TOWER C152 BHK525
TOWER C152 BHK565
TOWER C154 BHK1421
TOWER C162 BHK525
TOWER C162 BHK565
TOWER C164 BHK1421
TOWER C172 BHK525
TOWER C172 BHK565
TOWER C174 BHK1421
TOWER C182 BHK525
TOWER C182 BHK565
TOWER C184 BHK1421

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

PRITHVEELINK BUILDWELL PRIVATE LIMITED

CompanyPromoter type
2Registered projects
2Projects
1City
2017–2021Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
544 homeson the public record across 2 projects
11,095 sq mland declared
₹200.00 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Gautam Buddha Nagar
Tehsil
Gautam Buddha Nagar
Site access
Near Gaur International School
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.3km away
LifestyleNo parks within 2km
ShoppingSupermarket 454m away
Getting around
Expressway 2.2 km · FlyoverPrimary road 2.4 km · Faridabad-Noida-Ghaziabad ExpresswayRailway line 3.1 kmRailway station 3.7km away (Ghaziabad Junction)Limited bus connectivity nearby
Water & environment
Water body 995 mRiver 1.3 km · Hindon River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹80.00 Cr declared to build 209 flats. What that works out to:

₹38.28 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 14 Oct 2016 · 9 yrs ago
Building Permit no. PLG(BP) 3208/7567

The promised possession date (31 May 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Completion Certificate — the occupancy sign-off, on record

A Completion Certificateis on this project’s RERA record (dated 13 Jul 2020)— the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit before you rely on it.

Verify it yourself — look up plan PLG(BP) 3208/7567 on the approving authority’s portal to confirm the sanction.

Complaints register

1 complaint on UP-RERA’s register for this project.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.