HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Plots
50 plots
Land area
10,120 sq m
Description
As per Township Policy 2010, 6 plots (i.e. plot no. 41, 42, 43, 44, 45, 46.) admeasuring 501.67 square meters have been kept mortgage by कार्यालय नगरपालिका मंडल रावतसर जिला हनुमानगढ़(राजस्थान). These plots would be allotted after the internal development work is completed or development charges are deposited with कार्यालय नगरपालिका मंडल रावतसर जिला हनुमानगढ़ (राजस्थान). The Total Open Area is 4511.37 Square meters consisting of Park 507.25 square meters + Road & Path 4004.12. Since it is a plotted development project there is no parking details are required.

Timeline

Construction startSep 2024
RERA registeredJun 2025
Proposed completionMar 2026
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

50 plots across 11 batches
TypeArea sq mCount
Plot1,20014
Plot1,6002
Plot2,1006
Plot1,05012
Plot9004
Plot8702
Plot9006
Plot8001
Plot1,4001
Plot1,2001
Plot1,0001

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

VIKAS

IndividualPromoter type
Hanumangarh, RajasthanBased in
1Projects
1City
2025–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Chak No. 11 A M, Stone No. 166/410, Murbba No. 37, Killa No. 19.20,21,22, Hanumangarh, Rawatsar, Hanumangarh, 335524
Village
Hanumangarh
Taluka
Rawatsar
District
Hanumangarh
Pincode
335524
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 523m away · 2 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 45 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 1.5 kmCanal 1.6 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹1.16 Cr declared to build 50 plots. What that works out to:

₹2.33 Lakhdeclared cost per plotall-in — land + construction
₹107/sq ftof plotted area₹1,150/sq m

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Senior Town Planner

Town & Country Planning
Layout Permitapproved 5 Jun 2025 · 1 yr ago

The promised possession date (1 Mar 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Town Planning office

The state Senior Town Planner's office. It has approved 115 RERA projects across 18 districts about 1 in 19 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.