21 on filequarterly progress reports filed with RERA
Timeline
RERA registeredMar 2021
Proposed completionMar 2027
TodaySep 2026
Construction progress
90% overall, as filed
Security Service50%
Water Supply60%
Street Lighting90%
Energy Maanagement90%
Storm Water Drains95%
Landscaping And Tree Planting95%
Internal Roads And Footpaths100%
Sewerage100%
Solid Waste Management And Disposal100%
Water Conservation Rain Water Harvesting100%
Boundary Wall100%
From the builder's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.
Find your plot
Filed by type and size, in the batches the builder registered — not a per-plot listing. Look yours up.
113 plots across 40 batches
TypeArea sq mCount
Plot1581
Plot1612
Plot1601
Plot1571
Plot1531
Plot1451
Plot1381
Plot1621
Plot1861
Plot13737
Plot1811
Plot1421
Plot1028
Plot1171
Plot581
Plot919
Plot842
Plot1383
Plot1471
Plot1254
Plot872
Plot861
Plot921
Plot1521
Plot1601
Plot1681
Plot19512
Plot1941
Plot1951
Plot1961
Plot1971
Plot1771
Plot1541
Plot1791
Plot2232
Plot2111
Plot2031
Plot1891
Plot1823
Plot3041
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Primary road 239 mRailway line 1.2 kmRailway station 1.4km away (Dadhapara)Limited bus connectivity nearby
Water & environment
Canal 2.4 km · Arpa CanalWater body 2.6 km
distances only — not a flood assessment
Land, title & encumbrance
Mortgage12 unit(s) declared under mortgage to a bank/lender for project finance
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price
₹11.82 Cr declared to build 113 plots. What that works out to:
₹10.46 Lakhdeclared cost per plotall-in — land + construction
21%of the cost is land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Chhattisgarh registration department
In Chhattisgarh it’s called the collector guideline rate.
No government guidance rate is shown for this project.
Chhattisgarh's government guidance rates aren't in Horizon's record yet.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Complaints & litigation
RERA Chhattisgarh · public record
Complaints, as the builder reports them
None in the builder’s latest quarterly return to RERA Chhattisgarh.
The builder’s own count of grievances it received — not RERA Chhattisgarh’s register, which isn’t published. Cases the builder declares are listed below.
What the builder declared
Declared to RERA Chhattisgarh
Litigation
None declared in this filing
Only what the builder declared, or what RERA Chhattisgarh records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RERA Chhattisgarh, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
06
Other projects nearby
The register · within 25 km
103 plotted projects still under way within 25 km. Step out ring by ring:
Of the 68 projects the radar draws within 6 km — every kind, every stage — 22 are plotted projects still under way. This list keeps only those, and looks further out.