Complete project overview
RERA Karnataka · Registration filing- Status
- Ongoing
- Plots
- 302 plots
- Land parcels
- 15 survey nos
Timeline
Proposed completionMay 2027
Construction progress38% overall, as filed
From the promoter's latest quarterly progress report filed with RERA Karnataka — % complete overall and by stage, as of that filing. A dated snapshot, not a live tracker. UnitTypeTotal sq m
187Plot114.56
188Plot120.23
189Plot128.87
190Plot76.78
191Plot104.16
192Plot131.53
193Plot158.95
194Plot186.09
195Plot167.08
196Plot167.08
197Plot167.08
198Plot167.08
199Plot167.08
200Plot118.11
201Plot111.42
202Plot111.42
203Plot111.42
204Plot111.42
205Plot111.42
206Plot111.42
207Plot111.42
208Plot111.42
209Plot111.42
210Plot111.42
211Plot111.42
212Plot111.42
213Plot111.42
214Plot111.42
215Plot111.42
216Plot111.42
217Plot111.42
218Plot111.42
219Plot111.42
220Plot111.42
221Plot143.11
222Plot147.68
223Plot111.42
224Plot111.42
225Plot111.42
226Plot111.42
227Plot111.42
228Plot111.42
229Plot111.42
230Plot111.42
231Plot111.42
232Plot111.42
233Plot111.42
234Plot111.42
235Plot111.42
236Plot111.42
237Plot111.42
238Plot111.42
239Plot111.42
240Plot111.42
241Plot111.42
242Plot111.42
243Plot113.84
244Plot106.28
245Plot111.42
246Plot111.42
247Plot111.42
248Plot111.42
249Plot111.42
250Plot111.42
251Plot111.42
252Plot111.42
253Plot111.42
254Plot111.42
255Plot111.42
256Plot111.42
257Plot111.42
258Plot167.08
259Plot167.08
260Plot167.08
261Plot167.08
262Plot167.08
263Plot167.08
264Plot167.08
265Plot233.68
266Plot111.42
267Plot111.42
268Plot111.42
269Plot111.42
270Plot111.42
271Plot111.42
272Plot111.42
273Plot111.42
274Plot111.42
275Plot111.42
276Plot111.42
277Plot111.42
278Plot111.42
279Plot102.01
280Plot94.51
281Plot111.42
282Plot111.42
283Plot111.42
284Plot111.42
285Plot111.42
286Plot111.42
287Plot111.42
288Plot111.42
289Plot111.42
290Plot111.42
291Plot111.42
292Plot111.42
293Plot111.42
294Plot111.42
295Plot111.42
296Plot111.42
297Plot111.42
298Plot111.42
299Plot111.42
300Plot111.42
301Plot111.42
302Plot111.42
303Plot111.42
304Plot111.42
305Plot111.42
306Plot111.42
307Plot90.18
308Plot120.54
309Plot98.08
310Plot113.48
311Plot130.35
312Plot114.79
313Plot89.23
313/1Plot97.83
314Plot111.42
315Plot111.42
316Plot168.25
317Plot172.40
318Plot139.29
319Plot139.29
320Plot139.29
321Plot111.42
322Plot166.23
323Plot126.22
324Plot86.21
325Plot135.68
326Plot139.29
327Plot139.29
328Plot139.29
329Plot139.29
330Plot139.29
331Plot139.29
332Plot139.29
333Plot139.29
334Plot139.29
335Plot139.29
336Plot167.08
337Plot167.08
338Plot167.08
339Plot167.08
340Plot167.08
341Plot167.08
342Plot167.08
343Plot167.08
344Plot167.08
345Plot167.08
346Plot167.08
347Plot167.08
348Plot167.08
349Plot167.08
350Plot186.65
351Plot293.85
352Plot167.08
353Plot167.08
354Plot167.08
355Plot167.08
356Plot164.06
357Plot170.60
358Plot167.08
359Plot167.08
360Plot167.08
361Plot167.08
362Plot167.08
363Plot167.08
364Plot167.08
365Plot167.08
366Plot167.08
367Plot167.08
368Plot167.08
369Plot167.08
370Plot167.08
371Plot139.29
372Plot139.29
373Plot139.29
374Plot139.29
375Plot139.29
376Plot139.29
377Plot139.29
378Plot139.29
379Plot139.29
380Plot139.29
381Plot139.29
382Plot139.29
383Plot139.29
384Plot132.86
385Plot124.44
386Plot139.29
387Plot139.29
388Plot139.29
389Plot139.29
390Plot241.78
391Plot139.29
391/1Plot146.95
392Plot139.29
393Plot139.29
394Plot139.29
395Plot139.29
396Plot100.85
397Plot123.44
398Plot139.29
399Plot139.29
400Plot139.29
401Plot139.29
402Plot139.29
403Plot139.29
404Plot139.29
405Plot139.29
406Plot139.29
407Plot139.29
408Plot139.29
409Plot139.29
410Plot133.49
411Plot92.41
412Plot111.42
413Plot111.42
414Plot111.42
415Plot111.42
416Plot111.42
417Plot111.42
418Plot111.42
419Plot111.42
420Plot111.42
421Plot111.42
422Plot111.42
423Plot111.42
424Plot107.64
425Plot169.27
426Plot111.42
427Plot111.42
428Plot111.42
429Plot111.42
430Plot111.42
431Plot111.42
432Plot111.42
433Plot111.42
434Plot111.42
435Plot111.42
436Plot111.42
437Plot116.44
438Plot137.53
439Plot111.42
440Plot111.42
441Plot111.42
442Plot111.42
443Plot111.42
444Plot111.42
445Plot111.42
446Plot111.42
447Plot111.42
448Plot111.42
449Plot111.42
450Plot111.42
451Plot111.42
452Plot111.42
453Plot111.42
454Plot111.42
455Plot111.42
456Plot111.42
457Plot111.42
458Plot111.42
459Plot111.42
460Plot111.42
461Plot111.42
462Plot111.42
463Plot154.77
464Plot86.02
465Plot111.42
466Plot111.42
467Plot111.42
468Plot111.42
469Plot111.42
470Plot111.42
471Plot69.57
472Plot81.88
473Plot125.83
474Plot169.91
475Plot108.26
476Plot111.28
477Plot114.34
478Plot117.40
479Plot120.42
480Plot123.44
481Plot126.50
482Plot129.56
483Plot132.58
484Plot135.64
485Plot138.70
486Plot176.47
Complete project overview — done
02
Builder’s track record
RERA Karnataka · Promoter registrationGEOWN CASPER ESTATES LLP
Partnership FirmPromoter type
Bengaluru UrbanBased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion
2024202520262027today
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Builder's track record — done
03
Location & price analysis
RERA Karnataka · Registration filing- Taluk
- Maluru
- District
- Kolar
- Pincode
- 563130
- Address
- Sy nos 132/1, 132/3, 133/1, 144/1, 144/2, 144/3, 144/4, 146/1, 146/2, 146/3, 146/4, 148/3, 148/5, 148/6 and 195 of , Maliyappanahalli Village, Kasaba Hobli , Maluru , Kolar, Karnataka - 563130
What’s nearbySchoolsNo schools within 2km
HealthcareNearest hospital 3.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting aroundPrimary road 2.1 km · Kolar Malur RoadRailway line 4.6 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environmentWater body 473 m
distances only — not a flood assessment Land, title & encumbranceLandOwned + joint development (JDA)
ConversionConverted to non-agricultural
LitigationDeclared free of litigation
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict. Price analysisdeclared build cost — not a sale price
₹17.96 Cr declared to build 302 plots. What that works out to:
₹5.95 Lakhdeclared cost per plotall-in — land + construction
41%of the cost is land
Location & price analysis — done
04
Planning authority
RERA Karnataka · Approved building planMalur Planning Authority
Town & Country Planning (DTCP)approved 5 Mar 2024 · 2 yrs ago
Layout Permit no. 08/2023-24/1250Survey no. 132/1
The occupancy certificate — the proof that isn’t hereA sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
Verify it yourself — look up plan 08/2023-24/1250 on the approving authority’s portal to confirm the sanction.
The approving body, at scale
Malur Planning Authority
Town & Country PlanningHas approved 20 RERA projects — 0.2% of Karnataka.
a plotted-layout market — 0% apartments · 100% plotted layouts. Your plotted layout is this body's core business.
- Builders
- 18
- On record
- 0 flats · 2,807 plots
- Since
- 2025
More layout-heavy than Karnataka overall — 100% plots here vs 38% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
Planning authority — done
Complaints registerNone on record with RERA Karnataka against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.