UP-RERA · Registration filing
Units
144 units
Unit mix
68 × 3 BHK · 68 × 4 BHK · 8 × PENTHOUSE
Carpet area
170–403 sq mper unit, as filed
Floors
19
Blocks
8
Land area
12,175 sq m

Timeline

RERA registeredDec 2022
Project startedJan 2023
Proposed completionDec 2028
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

144 units across 72 batches
BuildingFloorTypeArea sq mCount
Tower A123 BHK1702
Tower A133 BHK1702
Tower A143 BHK1702
Tower A153 BHK1702
Tower A163 BHK1702
Tower A173 BHK1702
Tower A183 BHK1702
Tower A193 BHK1702
Tower A1103 BHK1702
Tower A1113 BHK1702
Tower A1123 BHK1702
Tower A1133 BHK1702
Tower A1143 BHK1702
Tower A1153 BHK1702
Tower A1163 BHK1702
Tower A1173 BHK1702
Tower A118PENTHOUSE3492
Tower A223 BHK1702
Tower A233 BHK1702
Tower A243 BHK1702
Tower A253 BHK1702
Tower A263 BHK1702
Tower A273 BHK1702
Tower A283 BHK1702
Tower A293 BHK1702
Tower A2103 BHK1702
Tower A2113 BHK1702
Tower A2123 BHK1706
Tower A2133 BHK1702
Tower A2143 BHK1702
Tower A2153 BHK1702
Tower A2163 BHK1702
Tower A2173 BHK1702
Tower A218PENTHOUSE3492
Tower B1GF4 BHK2141
Tower B114 BHK2141
Tower B124 BHK2142
Tower B134 BHK2142
Tower B144 BHK2142
Tower B154 BHK2142
Tower B164 BHK2142
Tower B174 BHK2142
Tower B184 BHK2142
Tower B194 BHK2142
Tower B1104 BHK2142
Tower B1114 BHK2142
Tower B1124 BHK2142
Tower B1134 BHK2142
Tower B1144 BHK2142
Tower B1154 BHK2142
Tower B1164 BHK2142
Tower B1174 BHK2142
Tower B118PENTHOUSE4032
Tower B2GF4 BHK2141
Tower B214 BHK2141
Tower B224 BHK2142
Tower B234 BHK2142
Tower B244 BHK2142
Tower B254 BHK2142
Tower B264 BHK2142
Tower B274 BHK2142
Tower B284 BHK2142
Tower B294 BHK2142
Tower B2104 BHK2142
Tower B2114 BHK2142
Tower B2124 BHK2142
Tower B2134 BHK2142
Tower B2144 BHK2142
Tower B2154 BHK2142
Tower B2164 BHK2142
Tower B2174 BHK2142
Tower B218PENTHOUSE4032

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

OMAXE LIMITED; ADVAY PROPERTIES PRIVATE LIMITED; AGASTHYA PROPERTIES PRIVATE LIMITED; AMOD BUILDERS PRIVATE LIMITED

CompanyPromoter type
31Registered projects
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Lucknow
Tehsil
Sarojini Nagar
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.6km away
LifestylePark 1.7km away
ShoppingNo supermarket within 2km
Getting around
Expressway 1.5 kmPrimary road 671 m · Sultanpur RoadRailway line 1.6 km · Varanasi–Sultanpur–Lucknow lineNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 1.6 km · Gomti River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹350.00 Cr declared to build 144 flats. What that works out to:

₹2.43 Crdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan

Lucknow Development Authority

Development Authority
approved 22 Nov 2022 · 3 yrs ago
Building Permit no. LDA/BP/21-23-3048
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan LDA/BP/21-23-3048 on the approving authority’s portal to confirm the sanction.

Complaints register

None on record with UP-RERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.