Complete project overview

GujRERA · Registration filing
Units
35 units
Mix
35 × 4 BHK Bunglows
Carpet area
140–146 sq mper-unit range, as filed
Blocks
8
Land area
6,340 sq m

Timeline

Project startedJan 2018
RERA registeredMar 2018
Proposed completionJun 2023
TodayJul 2026
Construction progress

100% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

35 units across 1 batch
TypeArea sq mCount
4 BHK Bunglows16135

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

MERCURY ENTERPRISE

PARTNERSHIP FIRMPromoter type
Vadodara, GujaratBased in
1Projects
1City
2018–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Vadodara
District
Vadodara
Pincode
390022
Address
FP NO 87, RS NO 95/1 PAIKITP 1 HARNI, VADODARA
What’s nearby
SchoolsNearest school 1.5km away · College or university 1.1km away
HealthcareHospital 1.0km away
LifestyleNo parks within 2km · Gym or sports centre 1.5km away
ShoppingNo supermarket within 2km
Getting around
Expressway 695 m · Vadodara Bypass FlyoverPrimary road 231 mRailway line 4.9 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 559 mWater body 726 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹20.47 Cr declared to build 35 flats. What that works out to:

₹70.00 Lakh – ₹1.10 Crdeclared unit pricerange on the filing — not a live asking price
₹58.47 Lakhdeclared cost per flatall-in — land + construction
41%of the cost is land₹1,240/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Vadodara Municipal Corporation

Municipal / Corporation
Building Permitapproved 19 Mar 2018 · 8 yrs ago

The promised possession date (30 Jun 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Building-Use (BU) permission — the occupancy sign-off, on record

7 of 8 blocks carry a Building-Use (BU) permission (latest 3 Sep 2022)— Gujarat’s legal-to-occupy sign-off. The remaining block is not shown as BU-cleared here; treat it as not-yet-occupiable until confirmed.

The approving body, at scale

Vadodara Municipal Corporation

Municipal Corporation

Has approved 1,372 RERA projectsabout 1 in 13 in Gujarat.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,133
On record
1,45,936 flats · 226 plots
Reach
4 talukas
Since
2006

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.