Complete project overview

UP-RERA · Registration filing
Units
78 units
Unit mix
34 × 2 BHK · 24 × 3 BHK · 16 × 4 BHK · 4 × PENTHOUSE
Carpet area
100–304 sq mper unit, as filed
Floors
9
Blocks
2
Land area
3,800 sq m

Timeline

Project startedJun 2015
RERA registeredAug 2017
Proposed completionOct 2018
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

78 units across 41 batches
BuildingFloorTypeArea sq mCount
BLOCK-C,TOWER-10BSMNT3 BHK1302
BLOCK-C,TOWER-10GF3 BHK1302
BLOCK-C,TOWER-10GF2 BHK1002
BLOCK-C,TOWER-1014 BHK1452
BLOCK-C,TOWER-1012 BHK1002
BLOCK-C,TOWER-1024 BHK1452
BLOCK-C,TOWER-1022 BHK1002
BLOCK-C,TOWER-1033 BHK1302
BLOCK-C,TOWER-1032 BHK1002
BLOCK-C,TOWER-1043 BHK1302
BLOCK-C,TOWER-1042 BHK1002
BLOCK-C,TOWER-1054 BHK1452
BLOCK-C,TOWER-1052 BHK1002
BLOCK-C,TOWER-1064 BHK1452
BLOCK-C,TOWER-1073 BHK1332
BLOCK-C,TOWER-1072 BHK1002
BLOCK-C,TOWER-1083 BHK1332
BLOCK-C,TOWER-1082 BHK1002
BLOCK-C,TOWER-109PENTHOUSE3041
BLOCK-C,TOWER-109PENTHOUSE2271
BLOCK-C,TOWER-11BSMNT3 BHK1332
BLOCK-C,TOWER-11GF3 BHK1332
BLOCK-C,TOWER-11GF2 BHK1002
BLOCK-C,TOWER-1114 BHK1452
BLOCK-C,TOWER-1112 BHK1002
BLOCK-C,TOWER-1124 BHK1452
BLOCK-C,TOWER-1122 BHK1002
BLOCK-C,TOWER-1133 BHK1332
BLOCK-C,TOWER-1132 BHK1002
BLOCK-C,TOWER-1143 BHK1332
BLOCK-C,TOWER-1142 BHK1002
BLOCK-C,TOWER-1154 BHK1452
BLOCK-C,TOWER-1152 BHK1002
BLOCK-C,TOWER-1164 BHK1452
BLOCK-C,TOWER-1162 BHK1002
BLOCK-C,TOWER-1173 BHK1332
BLOCK-C,TOWER-1172 BHK1002
BLOCK-C,TOWER-1183 BHK1332
BLOCK-C,TOWER-1182 BHK1002
BLOCK-C,TOWER-119PENTHOUSE3041
BLOCK-C,TOWER-119PENTHOUSE2271

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

PAHARI MATA SEHKARI AVAS SAMITI LTD

SocietiesPromoter type
1Registered projects
1Projects
1City
2017–2018Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Lucknow
Tehsil
Lucknow
What’s nearby
SchoolsNearest school 1.8km away · 5 educational institutions within 1km · College or university 422m away
HealthcareHospital 66m away · 1 clinic within 1km
LifestylePark 1.2km away · 20+ restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Mall 2.0km away · Convenience store within 500m
Getting around
Primary road 7 m · Ashok MargRailway line 1.8 kmMetro station 586m away (Hazratganj)Bus stop within 500m
Water & environment
Water body 840 mRiver 1.6 km · Gomti River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹17.50 Cr declared to build 78 flats. What that works out to:

₹22.44 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 25 Nov 2010 · 15 yrs ago
Building Permit no. 460/2010-11

The promised possession date (31 Oct 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 460/2010-11 on the approving authority’s portal to confirm the sanction.

Complaints register

None on record with UP-RERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.